Often yes, if the plant uses most of its power in daylight. Since 1 January 2026, Solar ATAP lets a TNB customer install rooftop solar up to 100% of its maximum demand, capped at 1,000 kW, under a 10-year contract, and non-domestic surplus is credited at the system marginal price, so self-use matters more than export. A tenant can apply if the TNB account is in its name, but needs the landlord's written consent for the roof.
Key takeaways
- Solar ATAP replaced NEM for new applicants from 1 January 2026; non-domestic systems go up to 100% of maximum demand, with a 1,000 kW cap.
- Surplus from a factory is credited at the system marginal price, so size the system to your daytime load.
- The applicant must be the registered TNB customer; accounts on tenant sub-meters in a multi-tenant scheme are not eligible.
- New Bandar Bukit Raja factories come with 9 or 15 kWp of solar, an EV charger and a rainwater tank per unit.
- Medium and high voltage users can also look at CRESS for long-term green electricity.
Is rooftop solar worth it for a Klang factory?
The scheme changed this year. SEDA says the Solar Accelerated Transition Action Programme (Solar ATAP) started on 1 January 2026; a non-domestic customer may install up to 100% of its maximum demand, subject to technical assessment and a 1,000 kW limit, and the contract runs 10 years, after which the system is for self-consumption only (SEDA). The ministry said there is no fixed quota, and that non-domestic users are credited at the system marginal price for what they export (The Edge).
That credit rule is the point for a factory. Power you use on site saves the full tariff, while power you export earns the lower system marginal price, so a plant that runs machines and air-conditioning through the day gains more than a warehouse that is mostly empty. Read twelve months of bills for daytime use and maximum demand first; our guide to factory power in kVA and amps explains the bill, and FactoryHub's factory power calculator helps estimate load.
Cash is not the only route. In April 2026 the ministry said non-domestic users can choose procurement models from installers, including solar leasing and rent-to-own, without upfront capital, and that medium, high and ultra high voltage users can consider the Corporate Renewable Energy Supply Scheme (CRESS) for long-term green electricity (The Star).
Is the factory roof suitable for solar?
Panels add weight and fixings to a roof that was designed years ago, so an engineer should confirm the purlins and trusses can carry them and that the sheets have enough life left to outlast a 10-year contract. Older units in Kapar, Meru and Klang town may still have roof sheets that need checking for asbestos before anyone drills into them; our guide to inspecting a used factory covers roof and steel life and the DOSH rules on asbestos.
SEDA's rules add two practical limits. The application is made through the SEDA eATAP system by a SEDA registered PV service provider, and only after the installation is fully completed and commissioned (SEDA). A roof that leaks or needs replacing should be fixed first, because lifting panels later costs money.
Can solar be installed on a rented factory in Klang?
Yes, if the TNB account is in the tenant's name and the landlord agrees. SEDA says the applicant must be a registered TNB consumer, and that accounts registered under tenant sub-meters in a multi-tenant scheme are not eligible (SEDA). A tenant of a whole detached or semi-D unit with its own meter can therefore apply; a tenant sharing a partitioned building on the landlord's meter usually cannot.
The roof belongs to the landlord, so put the deal in writing before any work: consent to the installation, who owns the panels, who insures them, who pays for roof repairs under them, and whether they stay or are removed when the tenancy ends. With a 10-year contract, a tenancy of three years plus three needs a clear answer on what happens at the end. Our guide to renovating a rented factory and reinstatement shows how Klang tenancies handle fixtures.
Which green features do Klang factories already offer?
In Bukit Raja, Sime Darby Property's brochure for the Masterpiece Collection semi-detached and detached factories in Bandar Bukit Raja Industrial Park 3 lists rooftop solar panels of 9 kWp or 15 kWp per unit depending on the type, one EV charging station per unit, a rainwater harvesting tank of 150 gallons, cross ventilation and skylights over the production area. The same brochure says the next stage is planned as a sustainable, ESG-focused managed industrial park (Sime Darby Property). FactoryHub keeps data on the Bukit Raja industrial area.
On Pulau Indah, FMM House is building three green logistics hubs with automated storage of about 1.67 million sq ft and 218,000 pallets, including ambient and cold rooms, pre-certified Gold under LEED, funded by green notes (The Star). In Bukit Raja, OMEGA 1 is described as offering ambient and cold chain capability under integrated automation (The Edge, June 2026). Most older units in Kapar, Meru and Port Klang have none of these features, so a tenant with ESG targets usually adds solar and metering itself.
Rainwater harvesting and flood resilience in Selangor
Rainwater harvesting is part of building plan approval in Selangor. A Selangor council's briefing explains that the Uniform Building By-laws 1984 were amended in by-laws 2, 10 and 115 so that a rainwater collection and reuse system (SPAH) is considered at design stage and checked as a condition of building plan approval (MPAJ). For a new factory or an extension in Klang, ask the architect what MBDK requires for your roof area before you design the drainage.
ESG reviews by multinational customers now ask about physical risk as well as energy. In Klang that means flood: a unit whose loading dock sits low beside a drain that backs up can stop shipments however green its roof is. Our flood checks for Kapar, Meru and Klang list the public records and the questions to ask before you sign.
General green and smart factory questions
These questions are the same anywhere in Malaysia, so here is the short answer with a link to FactoryHub's fuller guide.
- What is a green or ESG-compliant factory, and how do GBI, GreenRE and LEED differ? A building rated for energy, water and materials under a Malaysian (GBI, GreenRE) or US (LEED) scheme; see FactoryHub's guide to green-certified factories.
- Why do multinationals prefer green factories, and is the rent higher? Their own carbon and reporting targets drive it, and the premium depends on the building; the same FactoryHub guide covers costs, rents and value.
- What is a smart factory or an Industry 4.0 factory? One where machines, sensors and systems are connected and automated, which needs stable power, flat floors and fibre; see FactoryHub on Industry 4.0 factories in Klang.
- How will AI and robots change what a factory building needs? Mostly more power quality, floor flatness and clear height; see FactoryHub's automation-ready building checklist.
- What is built-to-suit factory investment? A developer or investor builds to the occupier's specification, usually against a long lease; see FactoryHub on built-to-suit versus ready factories.
Questions buyers and tenants ask
Can a Klang factory still join NEM?
Not as a new applicant. Solar ATAP replaced net energy metering for new applications from 1 January 2026, and SEDA says an applicant must not be registered under NEM or the self-consumption programme. An existing NEM customer should check its own contract before changing anything.
How big a solar system can a factory install under Solar ATAP?
Up to 100% of the account's maximum demand, subject to TNB's technical assessment, with a limit of 1,000 kW for non-domestic customers. Because exported power earns only the system marginal price, most factories size the system to their daytime use rather than to the maximum allowed.
Do new Bandar Bukit Raja factories come with solar and EV chargers?
The developer's brochure for the Masterpiece Collection in Bandar Bukit Raja Industrial Park 3 lists 9 kWp or 15 kWp of rooftop solar per unit, one EV charging station per unit and a 150 gallon rainwater harvesting tank. Check the sale and purchase agreement for what is actually included in the unit you buy.
Who owns the solar panels when a factory tenancy ends?
Whoever the tenancy says. With no written term, fixtures attached to the building can become a dispute, so agree in advance whether the tenant removes the panels and repairs the roof, sells them to the landlord, or leaves them. Match the answer to the 10-year Solar ATAP contract and the account holder.
Is there a quota for Solar ATAP in 2026?
No fixed quota was set, unlike the old NEM rounds, but the ministry said the government can impose a limit at any time if uncontrolled installation affects the national grid. Apply once the design and roof checks are done rather than waiting.
Can a factory in Kapar or Meru install an EV charging station?
Yes, as an electrical installation on your own supply, designed and tested by a registered electrical contractor. The practical limit is power: a fast charger adds load, so check your spare capacity in amps before you order one, and ask the landlord's consent in a rented unit.
Units in these places
- Detached Factory/Warehouse for Rent in Bukit Raja Selatan (near i-City Shah Alam), 133,971 sq ft · RM 241,148 / month
- Detached Factory/Warehouse for Rent in Bandar Bukit Raja, 8,387 sq ft, 200A · RM 26,000 / month
- Terrace Factory/Warehouse for Rent in Perigi Nanas, 2,949 sq ft · RM 4,500 / month
- Industrial Land for Rent in Pulau Indah, 0.45 acres · RM 6,000 / month
- Semi-D Factory/Warehouse for Rent in Ambang Botanic, 38,910 sq ft, 1000A · RM 71,984 / month
- All listings
Updated
Sources
- SEDA Malaysia: Solar ATAP, eligibility, capacity and tenure
- The Edge: Rooftop Solar ATAP programme open for application from Jan 1, 2026 (Dec 2025)
- The Star: Govt pushes Solar ATAP to shield consumers from power price shocks (Apr 2026)
- Sime Darby Property: Bandar Bukit Raja Industrial Park brochure
- The Star: UOB backs FMM House's RM3bil green notes to fund Pulau Indah logistics hubs (Aug 2025)
- MPAJ: Sistem Pengumpulan dan Penggunaan Semula Air Hujan (SPAH) under UKBS 1984
- The Edge: Industrial market insight special issue (Jun 2026)
Tell Ms Teh what you need