Renovating a rented Klang factory: consent, who owns the improvements, reinstatement works and the deposit
Ms Teh Seok Hoon, PEA 4006. Updated
Renovating a rented factory in Klang takes two consents: the landlord's, in writing, and the council's. MBDK's alteration plan checklist asks for the owner's letter allowing the tenant to renovate and a copy of the tenancy agreement. Anything permanently fastened to the building may be treated as part of the land, so agree in writing what you may remove, what you must reinstate at exit and how the deposit is settled.
Key takeaways
- Get the landlord's consent in writing before any work, then the council's: MBDK's checklist asks tenants for the owner's consent letter and the tenancy agreement.
- Act 133 makes altering a building without the council's written permission an offence, with a fine of up to RM25,000 and a possible order to alter or demolish.
- The National Land Code counts things permanently fastened to the land as part of the land, so the agreement must say what you may take away.
- Finish reinstatement works inside the term: a tenant holding over can be charged double rent under the Civil Law Act 1956.
- What a landlord keeps from the deposit must be reasonable compensation, capped at the sum the agreement names; agree an itemised exit list at a joint inspection.
- MBDK decision on alteration plans (non-residential)
- 7 days (client charter)
- Altering a building without permission (Act 133, s.70(11))
- Fine up to RM25,000; court order to alter or demolish
- Plan fees when work started first (Act 133, s.70(14))
- 5 to 20 times the prescribed fee
- Holding over after the tenancy ends (Civil Law Act 1956, s.28(4)(a))
- Double rent, at the landlord's option
- Scheduled wastes stored on site
- 180 days or less, up to 20 tonnes
- Tenancy exempt from registration (National Land Code, s.223)
- Term of up to 3 years
Why the tenancy agreement decides most of it
A factory tenancy in Malaysia is mainly a matter of contract. The tenancy law now being prepared is for homes: the Residential Tenancy Bill had still not been tabled in Parliament in August 2026, FMT reported. For a factory, what you may build, what you must take out at the end and how the deposit is settled come from the tenancy agreement, read with general laws such as the Contracts Act 1950, the National Land Code, the Civil Law Act 1956 and the Street, Drainage and Building Act 1974 (Act 133).
If your tenancy is for a term of up to three years, the National Land Code treats it as a tenancy exempt from registration, which may be made by a written instrument in any form, and an option to renew does not count towards the three years (sections 223 and 224). A lease for more than three years is a registrable interest under section 221. Either way, the renovation and exit terms are only as clear as the clauses you sign.
Stamp the agreement and every side letter that approves works or changes the exit terms. Under section 52 of the Stamp Act 1949, an instrument chargeable with duty that is not duly stamped cannot be admitted in evidence until the duty and any penalty are paid, which matters if a deposit dispute ever reaches court. FactoryHub's tenancy stamp duty calculator shows the duty for a given rent and term.
Two consents before work starts: the landlord and the council
Read the alteration clause before you plan the layout, then get the landlord's approval in writing for the actual drawings, not a general yes in a chat message. You will need that letter for the council as well.
In Klang the council application is made with the owner's documents. MBDK's checklist for alteration plans, in force since 1 April 2024, lists for shop houses and light industry the owner's letter allowing the tenant to renovate and a copy of the tenancy agreement. The same form asks for the owner's identity card, the latest paid assessment and quit rent receipts, an official search of the title, Form F (for buildings from 2007) or the Certificate of Fitness, plans submitted by a registered architect, engineer or draughtsman, and a contractor registered with CIDB. Where they apply, it adds approval letters from Bomba, from Indah Water and from DOSH (JKKP) for mechanical equipment, and a letter telling the neighbours about the work with an undertaking to repair any damage to their units.
MBDK is the council for most of her areas: its local plan names Bandar Klang, Pelabuhan Klang, Pulau Indah, Kapar and Meru among the main towns of its planning area (MBDK local plan summary). Its Building Department charter says alteration and addition applications for non-residential buildings are processed and decided within seven days. Bukit Raja Selatan is under Shah Alam's council instead, as her guide on which council covers Bukit Raja explains. Factories in Puncak Alam, including Taman Industri Alam Jaya, come under Majlis Perbandaran Kuala Selangor (MPKS) (NST), whose building plan guidance says construction may not start before MPKS approves the plan and that changes to an approved plan must be submitted for approval first.
Which works need approval, and what happens if you skip it
Act 133 starts from a short rule in section 70(1): no one may erect a building without the council's prior written permission. Section 70(16) spells out that this covers more than new buildings: additions or alterations that involve new foundations, an additional storey, and rebuilding or adding more than half of the area of walls and partitions or of upper floors or roofs all count. On a factory that can cover a roof over the yard on new columns, a new office block or an extra floor.
Other alterations are caught too: making any alteration to a building without the council's prior written permission can bring a fine of up to RM25,000, and a Magistrate's Court shall, on the council's application, order the building altered or demolished. Section 70(12) sets a fine of up to RM25,000, plus up to RM500 for every day after a notice, for using a building for a purpose other than the one it was built for without permission. Where work started without approval and no prosecution has begun, section 70(14) makes the plan fees five to twenty times the prescribed amount when the plans are finally submitted.
MBDK enforces this in the estates tenants rent in. In February 2025 its J-Force team checked 533 industrial premises in and around Sungai Kapar Indah, and by 14 February it had issued 527 compounds and 59 notices under Act 133 and council by-laws, The Star reported. The council told operators with illegal extensions to submit plans at once, and gave them the option to demolish the structures and restore the premises to their original state. Her guide to illegal extensions on a Klang factory explains how to check a unit for older unapproved additions before you sign.
Two other approvals sit beside the council's. Under section 32(2) of the Fire Services Act 1988, the occupier of designated premises who proposes a material change while a fire certificate is in force must notify Bomba before the work begins, and starting without that notice is an offence. If your layout adds racking, partitions or offices, check what it does to the fire systems first; her guide to fire protection in a Klang factory covers what Bomba looks at. For wiring, the Energy Commission registers electrical contractors under the Electricity Regulations 1994 and the Electricity Supply Act 1990 to keep installations safe and to monitor the competent persons who do the wiring. Use a registered contractor, keep its test records, and size any power upgrade with FactoryHub's factory power calculator before you ask the landlord.
Who owns the improvements when you leave
Section 5 of the National Land Code defines land to include all things attached to the earth or permanently fastened to anything attached to the earth. A mezzanine bolted to the slab, a roof over the yard, a built-in office or a new floor screed may therefore be treated as part of the land, which belongs to the registered owner, even though you paid for it. Whether a particular item is a fixture can be argued either way, so do not leave it to an argument at the end. If the landlord agrees to pay for anything you leave behind, put the sum or the formula in writing; without it you have no agreed basis to ask for payment.
Write a schedule of works into the agreement, or into the landlord's consent letter, that sorts every item:
- Items that stay and become the landlord's at the end, and whether the landlord pays anything for them.
- Items you may remove at the end, such as machines, racking, compressors, air conditioning units and signboards, and how holes and fixings will be made good.
- Items you must remove and reinstate, such as partitions, an office block or a mezzanine the landlord does not want, and the condition the floor, walls and roof must be returned to.
- Who insures the improvements during the tenancy, and who pays if the council orders any of them altered or removed.
What reinstatement works cover in a factory
Reinstatement works, also called make good, return the unit to the condition the agreement describes, for example the condition at handover with fair wear and tear excepted. The scope depends entirely on the wording, so ask for a dated schedule of condition with photos, together with the approved building plan, when you take the unit. It is the only fair yardstick at the end.
A reinstatement list for a factory or warehouse can include:
- Removing partitions, offices, mezzanines and fixings the landlord did not agree to keep, and patching the floor, walls and roof.
- Disconnecting your machines and making the electrical installation safe through a registered contractor, with the main switchboard returned in the agreed state.
- Clearing racking anchors, floor markings, signage and any materials left on site.
- Removing scheduled wastes properly: under the Environmental Quality (Scheduled Wastes) Regulations 2005, a waste generator may store scheduled wastes on site for 180 days or less and up to 20 tonnes, and they may be disposed of at prescribed premises only.
- Telling Bomba about any change to the fire systems, and handing over keys, access cards and the documents for approved works.
Finishing on time and getting the deposit back
Book contractors early, because the works must be finished before the tenancy ends. Under section 28(4)(a) of the Civil Law Act 1956, every tenant holding over after the end of the tenancy can be charged, at the landlord's option, double the rent until possession is given up, or double the value for the period the premises are kept. If you need more time, agree a short extension in writing before the end date.
For an older unit with additions left by a previous tenant, settle at the start whether you will be asked to remove them. Otherwise you may be asked to reinstate works you never built.
The deposit is set by the agreement, and so is what the landlord may deduct. When a contract names a sum to be paid on breach, section 75 of the Contracts Act 1950 entitles the party complaining of the breach to reasonable compensation not exceeding that sum, whether or not actual loss is proved. In plain terms, the landlord need not prove every ringgit, but what it keeps must still be reasonable compensation. That is why an itemised list of deductions with quotes or invoices matters more than the size of the deposit.
Write into the agreement how many days after handover the deposit is refunded, how deductions are shown, and that a joint inspection takes place before the end date. Do the inspection with the schedule of condition in hand, list what is outstanding, and get each item signed off as it is done.
If you cannot agree, a deposit claim is an ordinary civil claim. Under the Subordinate Courts Act 1948, a First Class Magistrate hears civil claims of up to RM100,000, and a Sessions Court has unlimited jurisdiction in landlord and tenant actions and in distress.
A landlord also cannot simply lock up your goods. Section 4 of the Distress Act 1951 says no landlord shall distrain for rent except as the Act provides: the landlord applies to a Judge or Registrar for a warrant of distress covering rent for up to twelve completed months, and a bailiff carries it out (sections 5 and 7). After a tenancy ends, the owner can recover possession from an occupier who stays on only through court proceedings (Specific Relief Act 1950, section 7(2)).
A checklist before you sign and before you leave
Use these points with the landlord and your lawyer. They follow from the rules above and are not legal advice for your case.
Before signing: ask for the approved building plan and the CCC or Certificate of Fitness, and compare them with the unit. Existing unapproved additions raise the question of who removes them.
Before signing: write the renovation clause around your real drawings, with the lists of items, who applies to MBDK or MPKS, who pays the consultant and fees, and how quickly the landlord signs the owner's letter.
Before work starts: get the council permit, notify Bomba of any material change, use a CIDB registered builder and an Energy Commission registered electrical contractor, and check racking or mezzanine loads with FactoryHub's floor loading calculator.
During the tenancy: keep every approval, drawing and invoice; they are your proof at the end.
Three to six months before the end: agree the reinstatement scope in writing, book contractors and plan the disposal of scheduled wastes.
At handover: a joint inspection against the schedule of condition, a signed list of outstanding items and a date for the deposit refund.
Ms Teh can help tenants find factories and warehouses in Kapar, Meru and the rest of Klang whose plans, approvals and handover condition can be checked before you commit.
Questions buyers and tenants ask
Do I need my landlord's consent to renovate a rented factory in Klang?
Yes, in practice twice. Your tenancy agreement sets when the landlord's written approval is needed, and MBDK's alteration plan checklist asks tenants for the owner's letter allowing the renovation and a copy of the tenancy agreement, together with the owner's identity card, a title search and paid assessment and quit rent receipts. Without the owner's documents the plan cannot be submitted.
Who owns the mezzanine or office I built when the tenancy ends?
Unless the agreement says otherwise, anything permanently fastened to the building may be treated as part of the land, because the National Land Code defines land to include things attached to the earth or permanently fastened to them. Agree in writing which items you may remove, which stay, and whether the landlord pays anything for them.
Is make good the same as reinstatement works?
Both phrases describe the tenant's duty at the end to return the unit in the condition the agreement sets. What that covers is whatever the clause and its schedule say, so read the wording and the condition report rather than the label.
Can the landlord charge more if reinstatement runs past the end date?
Yes. Section 28(4)(a) of the Civil Law Act 1956 lets a landlord charge a tenant holding over after the tenancy ends double the rent until possession is given up. Finish the works inside the term or agree an extension in writing before the end date.
Can the landlord keep my machines until I pay for reinstatement?
Not on its own. The Distress Act 1951 says a landlord may distrain for rent only as the Act provides, through a court warrant of distress carried out by a bailiff, and after the tenancy ends an owner recovers possession from an occupier only through court proceedings under the Specific Relief Act 1950. A claim for reinstatement costs is a contract claim, which is why an agreed exit list matters.
My factory is in Puncak Alam or Bukit Raja Selatan. Who approves my renovation?
Puncak Alam estates such as Taman Industri Alam Jaya come under Majlis Perbandaran Kuala Selangor (MPKS), and Bukit Raja Selatan comes under Shah Alam's council (MBSA). Klang town, Port Klang, Pulau Indah, Kapar and Meru are in MBDK's planning area. Confirm the council from the assessment bill before you appoint a consultant.
Can I make structural changes after renting a factory in Klang?
Only with two consents. The landlord must agree in writing, and work with new foundations, an extra floor or a new roof over the yard needs the council's prior written permission under section 70 of Act 133, from MBDK in Klang. If a fire certificate is in force, Bomba must be told before a material change. MBDK's J-Force checked 533 premises around Sungai Kapar Indah in February 2025 and issued 527 compounds.
Is it cheaper to rent a ready-built factory in Klang or to renovate one myself?
Price the months, not just the works. Renovating means council approval before work starts, then building, racking and fire systems, and every month of it is rent paid with no production unless you agree a rent-free fit-out period. At the end you may have to reinstate. A ready-built unit that already has your power, floor and loading bays usually costs less overall, even at a higher rent.
Units in these places
- Semi-D Factory/Warehouse for Rent in Ambang Botanic, 38,910 sq ft, 1000A · RM 71,984 / month
- Factory/Warehouse for Rent in Bandar Baru Klang, 65,000 sq ft, 1000A · RM 110,500 / month
- Detached Factory/Warehouse for Rent in Kapar Bestari, 22,462 sq ft, 200A · RM 50,000 / month
- Industrial Land for Sale in Kapar, 2.34 acres · RM 8,658,005
- Semi-D Factory/Warehouse for Rent in Meru, 25,700 sq ft, Medium Industrial · RM 48,000 / month
- All listings
Updated
Sources
- MBDK: Borang Senarai Semak Pelan Ubahsuai (PS2024), in force 1 April 2024
- MBDK: Jabatan Bangunan, functions and client charter
- MBDK / PLANMalaysia: Ringkasan Eksekutif Draf RTMPK 2035 (Penggantian) (Feb 2024)
- Majlis Perbandaran Kuala Selangor: Panduan, building plan requirements
- NST: MPKS leads another crackdown against businesses run by foreigners, Taman Industri Alam Jaya (Apr 2025)
- AGC: Street, Drainage and Building Act 1974 (Act 133)
- AGC: Fire Services Act 1988 (Act 341)
- PKNS e-Perundangan: National Land Code (Revised 2020) (Act 828)
- AGC: Civil Law Act 1956 (Act 67)
- AGC: Contracts Act 1950 (Act 136)
- AGC: Specific Relief Act 1950 (Act 137)
- AGC: Distress Act 1951 (Act 255)
- AGC: Subordinate Courts Act 1948 (Act 92)
- AGC: Stamp Act 1949 (Act 378)
- DOE: Environmental Quality (Scheduled Wastes) Regulations 2005, P.U.(A) 294/2005
- Suruhanjaya Tenaga (ECOS): Pendaftaran kontraktor elektrik
- The Star: MBDK cracks down on illegal factory extensions in industrial areas (Feb 2025)
- FMT: Don't delay tabling Residential Tenancy Bill to 2027, NGO tells govt (Aug 2026)