Illegal extensions on a Klang factory: spotting them, council action, loan, insurance, CCC and regularisation
Ms Teh Seok Hoon, PEA 4006. Updated
An unapproved extension is any addition or alteration built without the council's written permission under Act 133. In Klang, MBDK can compound, prosecute and order demolition, and in 2025 it told factory owners around Sungai Kapar Indah to submit plans or pull illegal structures down. Unapproved work sits outside the CCC and can lower the bank valuation and complicate insurance. Regularising means an amendment plan by a consultant, Bomba approval and a multiplied plan fee.
Key takeaways
- Under Act 133, adding to or altering a factory without the council's written permission is an offence, and the land owner is presumed responsible for the structure.
- In February 2025 MBDK's J-Force checked 533 premises around Sungai Kapar Indah and told owners with illegal extensions to submit plans or demolish.
- Occupying, or letting anyone occupy, a building without a CCC carries a fine of up to RM250,000; banks ask for the CCC and valuers may not count unapproved work.
- Tell Bomba before altering a premises that holds a fire certificate, and tell your insurer: cover is priced on the building and its fire protection.
- Regularising needs a consultant's amendment plan, supporting approvals and a multiplied plan fee (5 to 20 times under the Act, 10 times in MPKS); parts inside the setbacks may have to go.
- Altering a building without permission
- Fine up to RM25,000 and a court order to alter or demolish (Act 133, s70(11))
- Occupying without a CCC
- Fine up to RM250,000, up to 10 years' jail, or both (s70(27)(f))
- Plan fee when work started before approval
- 5 to 20 times the prescribed fee (s70(14)); MPKS warns of 10 times
- MBDK decision on non-residential additions
- Within 7 days (client charter)
- MBDK operation in Kapar, February 2025
- 533 premises checked; 527 compounds and 59 notices by 14 February
What counts as an unapproved extension on a factory
Section 70 of the Street, Drainage and Building Act 1974 (Act 133) says no one may erect a building without the local authority's prior written permission, and the Act means more than new buildings. Under section 70(16), adding to or altering an existing building in a way that involves new foundations or a new or partly new roof, building an extra storey, rebuilding or adding to more than half of the wall area or of the upper floor or roof area, and deviating from any approved plan all count as erecting a building, as the Act 133 reprint published by KPKT sets out. Works done on the same building two or more times within ten years can be added together.
On a factory that covers most of what owners add over the years: a steel roof over a side or rear yard, a closed-in loading area, an extra office floor or mezzanine, a raised roof or a larger guardhouse. Section 70(17) presumes, until the contrary is proved, that the owner of the land put the structure up, and makes that owner responsible for it. A buyer therefore takes on what a former owner built, and a landlord answers for what a tenant added unless it can be shown otherwise.
Which council you deal with depends on the address. Klang town, Kapar, Meru, Port Klang, Pandamaran and Pulau Indah are under Majlis Bandaraya Diraja Klang (MBDK). Bukit Raja Selatan is under Shah Alam's council (MBSA), as her guide on which council covers Bukit Raja explains, and the estates of Puncak Alam are under Majlis Perbandaran Kuala Selangor (MPKS). All three work under Act 133 and the Selangor Uniform Building By-Laws, each with its own forms and fees.
How to spot one before you buy or rent
The test is easy to state: what stands on site must match the approved building plan and any approved amendment plans. Ask the owner for both, together with the occupation certificate. MBDK's alteration checklist asks for a copy of Form F, the CCC form, for developments from 2007 onwards and for the Certificate of Fitness (CF) for older ones. In MBDK's area an owner can apply to the Building Department with its form for a copy of the CF: RM100 for a plain copy or RM200 for one certified by the council, for a business licence application or the owner's own record.
Then walk the unit with the plan in hand. Count the bays, check the roof line and height, and look at every mezzanine, office block, canopy, shed and guardhouse. MBDK's checklist for alteration plans, in force since 1 April 2024, sets these clearances to the lot boundary in its section on shophouses and light industry, for semi-detached and detached factories, warehouses and other industrial buildings, and its building plan checklist sets the guardhouse rules:
An addition that reaches inside those lines does not meet the checklist MBDK uses for addition plans. Also compare the built-up area in the sale or tenancy papers with the plan, and ask the owner in writing whether MBDK has served any notice or compound under Act 133 on the lot, and whether an amendment plan is pending. If the addition is a mezzanine or a floor for heavy stock, her guide to factory floor loading explains what it must carry.
- Walls: 12.192 m (40 ft) from the front boundary, 6.096 m (20 ft) or 7.62 m (25 ft) from the side and rear, and 12.192 m on the side of a corner lot.
- Roof eaves: 10.392 m (34 ft) at the front, 4.3 m (14 ft) or 5.79 m (19 ft) at the side and rear, and 10.392 m on the side of a corner lot.
- Guardhouse: at most 3 m by 4 m and single storey, no setback on the side facing the road but 3 m from a neighbouring lot, roof projecting no more than 500 mm past the lot boundary, foundations inside the lot.
- Anything standing outside the lot, for example on state land, is a matter for the land office as well as the council (see the next section).
What MBDK and the land office can do
Act 133 gives the council several tools. Under section 70(11), altering a building without written permission can bring a fine of up to RM25,000, and a Magistrate's Court must, on the council's application, order the building altered or demolished. Erecting a building in breach of the Act or deviating from approved plans carries a fine of up to RM50,000, up to three years' jail or both, plus RM1,000 for each day the offence continues after conviction (section 70(13)). Using a building for a purpose other than the one it was built for, without permission, carries up to RM25,000 plus RM500 a day after a notice (section 70(12)).
Section 72 lets the council serve the land owner a notice to stop work and demolish within a set time. Failing to comply costs up to RM250 for each day after the deadline, and the council may then demolish the structure itself and recover the costs from the owner, after giving the occupants at least 30 days' notice to vacate.
MBDK uses these powers in the industrial estates. In February 2025 its J-Force team, a 50-strong joint enforcement unit formed in March 2022, checked 533 industrial premises in and around Sungai Kapar Indah, The Star reported. By 14 February it had issued 527 compounds and 59 notices under Act 133 and the council's by-laws, for offences that included illegal extensions and building storage areas without a licence. Owners with illegal extensions were told to submit their building plans immediately for assessment under Act 133, or to demolish the structures and restore the property to its original state. FactoryHub's page on the Kapar and Sungai Kapar Indah industrial area describes that estate, and her Kapar page covers the wider town.
Structures on state land go to the land office, and that route can end in demolition. In May 2026 the Selangor Land and Mines Office (PTGS) and the Klang District and Land Office led a five-day operation with about 300 personnel to demolish 19 illegal factories on state land at Telok Gong, Pulau Indah, whose temporary occupation licences had expired 15 to 20 years earlier, The Star reported. The first notice had gone out in March 2025, and an enforcement officer cited section 425 of the National Land Code, which carries up to five years' jail, a fine of up to RM500,000, or both. A year earlier the state said it would not grant ownership status to 68 factories built on state land without a temporary occupation licence, 17 of them in Klang, according to a Bernama report in The Star. Her Telok Gong page and FactoryHub's Telok Gong area data cover the area.
Effect on the CCC, the loan, insurance and the fire certificate
A Certificate of Completion and Compliance (CCC) can only be issued by the principal submitting person, the architect or engineer who must first make sure the building was built to the approved plans and is safe and fit for occupation (section 70(20) and (21)). An extension that was never on an approved plan is outside that certificate. Section 70(27)(f) makes it an offence to occupy, or permit anyone to occupy, a building or any part of it without a CCC, with a fine of up to RM250,000, up to ten years' jail or both. For a landlord, the words "permit to occupy" are the ones to note. How a CF differs from a CCC, and what renting a unit with neither means, is in renting a factory without a CCC or CF.
Banks lend against a valuation and the documents. The Star reported in 2022, quoting Ampang Jaya's council building director, that banks ask for documents including the CCC before granting a housing loan, that unapproved works are not in the building plan so the valuation can come in below the quoted price, and that owners run into problems when selling or transferring because all building works, renovations and extensions included, need a CCC. The report was about houses, but the same Act 133 applies to factories in Klang. Before you sign, ask your bank whether its valuer will count the extension and what papers it needs to see for it.
Fire insurers look at the building too. Lulu Loke's guide to business fire insurance notes that factory cover is priced mainly on the construction, the nature of the work, the materials stored, fire protection and sums insured, and that for premises that need a fire certificate, a valid one affects whether and how insurers accept the risk. Under standard fire policy conditions, a change of trade or occupation that raises the fire risk must be endorsed on the policy, or cover for that property stops, and sums insured should be reviewed after renovations so the average clause does not cut a claim. The same 2022 report noted that insurance claims can be affected when renovations are done without approval.
Bomba's rules sit on top. Under the Fire Services Act 1988 every designated premises needs a fire certificate, renewable each year (section 28), and the owner commits an offence if none is in force (section 33). Section 32 requires the occupier to give Bomba notice before starting a material alteration to designated premises that hold a certificate; starting without notice is an offence, and if fire safety becomes inadequate Bomba can direct the steps to fix it and cancel the certificate if they are not taken. The 1998 designated premises order lists single-storey factories of 2,001 m² and above fitted with automatic sprinklers, and storage buildings of more than 7,000 m³, so an extension can also bring a building onto the list.
Your trading licence depends on the building as well: MBDK's Building Department checks and coordinates its department's support for business licences, and her guide to MBDK's industrial licence explains the conditions a licensed factory or warehouse must keep.
How regularisation works in Klang, step by step
Regularising means getting approval after the fact for what was built, as an amendment to the approved plan, and removing what cannot be approved. In MBDK's area the order runs like this:
Puncak Alam follows the same pattern under MPKS, whose building plan guide warns that works may not start before approval and that starting early can cost ten times the plan processing fee under the Uniform Building By-Laws. Not everything can be legalised: parts that break the setbacks, sit outside the lot or stand on state land have to be cut back or removed, which was the other option MBDK gave Kapar owners in 2025. Whole factories built without approval are handled by Selangor's standing committee on unauthorised factories (kilang tanpa kebenaran, KTK), whose chairman said in May 2025 that their number had fallen from over 6,000 to 4,170.
- Appoint a consultant. MBDK's alteration checklist lets a building draughtsman registered with the Board of Architects (LAM) submit additions of up to 300 m² (3,229 sq ft) of floor, on buildings of no more than two storeys, with reinforced concrete or steel spans of no more than 2.5 m. Anything larger must be submitted by an architect or engineer.
- Measure what stands and draw an amendment plan to the approved plan: new work in red, work to be demolished in blue dashed lines, each amendment numbered in a table, and the original approval conditions noted. For a factory or warehouse the plan title must state the activity and the goods produced.
- Collect the supporting approvals the checklist asks for where they apply: Bomba's approval letter and plan, Indah Water, DOSH (JKKP) approval for mechanical equipment, and a support letter from MBDK's planning or engineering department if floors or height are added or the whole building changes. A reinforced concrete roof needs structural plans and calculations by an engineer.
- A tenant can apply with the owner's written consent and the tenancy agreement, and an addition on a shared boundary needs the owner's undertaking that the neighbours on both sides were shown the plans.
- Pay the fees. MBDK's fee form charges RM14 per 9 m² for the ground floor (minimum RM140) and RM12 per 9 m² for the first floor, half rate for buildings with open sides such as factories, warehouses and open sheds, and RM120 for each amendment application plus the area rate on added floor area. It adds a plan multiple where work started before approval: section 70(14) of Act 133 sets five to twenty times the prescribed fee when the owner is not prosecuted. As an illustration, 900 m² of added ground floor at the full rate is RM1,400 in area fees, or RM7,000 to RM28,000 at five to twenty times, before consultants' fees.
- Wait for the decision. MBDK's client charter decides alteration and addition applications for non-residential buildings within seven days.
- Finish and certify. MBDK issues a certificate of works completion (Perakuan Siap Kerja) for alterations, and new building works close with Form F, the CCC. Then notify Bomba if the premises hold a fire certificate, update the insurer, and keep the approved plans with the title.
What buyers, tenants and owners should settle before signing
Who carries the problem depends on your side of the deal. The points below follow from the rules above.
Ms Teh can help you find factories and warehouses in Kapar, Meru, Port Klang and Puncak Alam whose plans and certificates you can check before you commit.
- Buyers: ask for the approved plans, any amendment approvals and the CF or CCC before the sale and purchase agreement, ask in writing about notices and compounds, and get the bank's view on whether its valuer will count the additions before you commit.
- Tenants: get the landlord's written consent before adding anything, since MBDK's checklist asks for it on a tenant's application, and agree in the tenancy who regularises or removes existing additions and who pays if a notice arrives. Section 72 notices go to the land owner, but the council must give occupants 30 days' notice before it demolishes, so your operation is directly affected.
- Owners and landlords: regularise before you sell or let. Section 70(27)(f) covers anyone who permits occupation without a CCC, and MBDK's own CF copy form lists business licence applications as a reason tenants need the papers.
Questions buyers and tenants ask
Can I renovate inside my factory in Klang without a permit?
It depends on the work. Under section 70(16) of Act 133, new foundations, a new or partly new roof, an extra storey, rebuilding more than half of the walls or floor area, and any deviation from the approved plan count as erecting a building and need written permission. MBDK processes alteration plans through a consultant or its standard plan book, so ask its Building Department before you start.
Will a bank lend on a factory with an unapproved extension?
Banks decide case by case, but they lend against a valuation and documents. The Star reported in 2022 that banks ask for the CCC before granting a housing loan and that unapproved works can bring the valuation below the quoted price. Ask your bank early whether its valuer will count the extension.
Who pays if the council orders a tenant's extension demolished?
Act 133 presumes the land owner erected the structure unless shown otherwise, and section 72 notices and demolition costs fall on the owner. Between landlord and tenant, the tenancy agreement decides who bears the cost in the end, so write it in before any work starts.
How long does MBDK take to approve an addition plan for a factory?
MBDK's client charter says alteration and addition applications for non-residential buildings are decided within seven days. The approvals the checklist asks for first, such as Bomba's plan approval, come from those agencies.
My factory is in Puncak Alam or Bukit Raja Selatan. Which council do I go to?
Puncak Alam is under Majlis Perbandaran Kuala Selangor (MPKS), which warns of ten times the plan processing fee if works start before approval. Bukit Raja Selatan is under Majlis Bandaraya Shah Alam (MBSA), while Bandar Bukit Raja is under MBDK. All three apply Act 133.
Units in these places
- Detached Factory/Warehouse for Rent in Kapar Bestari, 22,462 sq ft, 200A · RM 50,000 / month
- Industrial Land for Sale in Kapar, 2.34 acres · RM 8,658,005
- Semi-D Factory/Warehouse for Rent in Ambang Botanic, 38,910 sq ft, 1000A · RM 71,984 / month
- Factory/Warehouse for Rent in Bandar Baru Klang, 65,000 sq ft, 1000A · RM 110,500 / month
- Factory/Warehouse for Rent in Telok Gong, 48,063 sq ft, Medium · RM 82,000 / month
- All listings
Updated
Sources
- KPKT: Akta Jalan, Parit dan Bangunan 1974 (Akta 133), reprint with amendments to P.U. (A) 394/2010
- MBDK: Jabatan Bangunan, functions and client charter
- MBDK: Borang Senarai Semak Pelan Ubahsuai (PS2024), in force 1 April 2024
- MBDK: Senarai semak permohonan pelan bangunan and fee calculation form (2024)
- MBDK: Borang Permohonan Salinan Sijil Layak Menduduki (CF)
- MBDK: Akujanji Pemilik for additions on a shared boundary
- MPKS: Panduan, building plan requirements and warnings
- KPKT: Akta Perkhidmatan Bomba 1988 (Akta 341)
- KPKT: P.U. (A) 276/1998 Perintah Perkhidmatan Bomba (Premis Ditetapkan) 1998
- The Star: MBDK cracks down on illegal factory extensions in industrial areas (Feb 2025)
- The Star: Selangor demolishes long-standing illegal factories in Pulau Indah (May 2026)
- The Star (Bernama): Selangor to begin enforcement against 68 illegal factories in July, says exco (May 2025)
- The Star: Get approval for renovations or face hassles when selling house (Aug 2022)
- Lulu Loke: Fire insurance for a shop or factory, how much to insure (Nov 2026)
- Lulu Loke: Fire insurance questions, factory pricing and fire certificates