Renting a factory without CCC or CF in Klang: can a tenant get a licence, a fire certificate and insurance?

Ms Teh Seok Hoon, PEA 4006. Updated

Usually not on a normal application. MBSA asks for a copy of the CCC or CF with a licence application, MPKS sends units without one to its slower composite licence, and a designated factory cannot complete its Bomba fire certificate application without a copy of either. In MBDK's area, unapproved factories inside Selangor's legalisation programme can hold a one-year KTK licence at three or five times the normal fee. Occupying a building without a CCC is an offence for tenant and landlord.

Key takeaways

  • Occupying a building without a CCC, or permitting someone to occupy it, is an offence under section 70(27)(f) of Act 133: a fine of up to RM250,000, up to ten years' jail or both.
  • Older buildings carry a CF from the council instead of a CCC. Councils and Bomba accept either, so ask for a copy before you pay any deposit.
  • MBSA wants a copy of the CCC or CF with a licence application, MPKS checks the building's status first, and MBDK's Building Department supports every business licence.
  • A designated factory or store needs a yearly Bomba fire certificate, and the application asks for a copy of the CCC or CF.
  • Unapproved factories in MBDK's area can be licensed only inside Selangor's legalisation programme: one year at a time, at three or five times the normal fee.
Factory and warehouse hall
Factory and warehouse hall · Illustrative image
Occupying without a CCC (Act 133, s.70(27)(f))
Fine up to RM250,000, jail up to 10 years, or both
Copy of a CF from MBDK
RM100, or RM200 certified
MBDK KTK industrial licence
One year, renewable; 3x the normal fee inside an industrial zone, 5x outside
Bomba fire certificate
Valid 12 months; renew at least 30 days before expiry
Selangor deadline to legalise unauthorised factories
31 December 2027

CCC, CF and which council checks them in Klang

A Certificate of Completion and Compliance (CCC) confirms that a building was put up to its approved plans and is safe and fit to occupy. Under section 70(20) and (21) of the Street, Drainage and Building Act 1974 (Act 133), only the principal submitting person, the architect or engineer who submitted the plans, may issue it, after supervising the works and making sure the council's technical conditions were met. Buildings completed under the older system hold a Certificate of Fitness for Occupation (CF, Sijil Layak Menduduki) issued by the council itself. MBDK's Building Department still deals with both: it receives Form F for a CCC, and its client charter promises a CF within 14 days of receiving Form E.

For a tenant the point is that the certificate covers the building as approved. An older factory holding a CF is covered for what was approved at the time. A factory whose later extension, mezzanine or second block was never approved is only partly covered, and her guide to illegal extensions on a Klang factory shows how to spot them. A factory put up without any approval, what Selangor calls a kilang tanpa kebenaran (KTK), has no certificate to show at all.

Which council checks depends on the address. Klang town, Kapar, Meru, Port Klang, Pandamaran and Pulau Indah are under Majlis Bandaraya Diraja Klang (MBDK). Bukit Raja Selatan is under Majlis Bandaraya Shah Alam (MBSA) while Bandar Bukit Raja is under MBDK, as her guide Bukit Raja: Klang council or Shah Alam council? explains, and Puncak Alam is under Majlis Perbandaran Kuala Selangor (MPKS). Each council runs its own licensing desk, and each looks at the building before it licenses the business inside.

Can a tenant get a business licence without a CCC or CF?

Not through the normal route. The three councils ask about the building in different ways, but all three ask:

In MBDK's area an industrial licence starts as a temporary licence, after which the operator collects documents from up to ten agencies, the Building Department among them. Her guide to MBDK's industrial licence lists them. A unit with no CCC or CF has nothing to show at the building step, which is why the unapproved factories in Klang are licensed through a separate route.

  • MBSA (Bukit Raja Selatan): its composite licence page lists a copy of the CCC or CF, and a building permit where one applies, among the documents for a business or industrial licence, with four copies of each document.
  • MPKS (Puncak Alam): its licensing forms page keeps the instant licence for low-risk trades in premises with a CF or CCC. Factories doing industrial work, and premises with neither certificate, apply for the composite licence, which MPKS aims to decide within 45 working days against 24 hours for an instant licence. Where the original certificate is missing, MPKS's Building Control Department must first confirm the building's status on a separate form.
  • MBDK (Klang, Kapar, Meru, Port Klang, Pulau Indah): the Building Department checks and coordinates its support for every business licence, and the council's form for a copy of the CF, in force since 1 April 2024, names a business licence application as the first reason to ask for one. A copy costs RM100, or RM200 certified by MBDK.

The KTK licence: how unapproved factories in Klang stay licensed

Selangor has known for years that many factories run without approval. Its programme to legalise them began in 2006. In January 2025 the state said 6,690 unauthorised factories stood on 5,352 lots identified up to 2019, gave them until 31 December 2025 to start registering and until 31 December 2027 to legalise, and said factories set up after 2019 are not eligible, The Star reported. The incentives include a 30% discount on the premium for converting land use, special land permits and temporary licences. By May 2025 the count had fallen to 4,170, Bernama reported in The Star.

MBDK licenses factories inside that programme on its own terms. Its statutory declaration for a KTK industrial licence sets out what the operator accepts:

The 2025 renewal checklist, in force from 5 November 2024, asks Category A factories for an official title search or a land conversion application or approval from the Klang District and Land Office, and Category B factories for a special temporary permit from the same office. Both also need last year's MBDK licence, the planning permission and building plan applications or approvals, or the CCC, and letters from the Department of Environment, Bomba and DOSH. For a tenant this means a KTK unit can be licensed, but at a higher fee, one year at a time, and only while the owner keeps the legalisation moving.

  • The licence lasts one year and must be renewed every year, if the council approves.
  • The fee is three times the normal industrial licence fee for a Category A factory, inside an industrial zone, and five times for a Category B factory outside one.
  • While licensed, the operator must apply for land conversion, planning permission, building plans and road and drainage plans, and obtain licensing support from Bomba's Klang zone office, the Department of Environment (JAS) and DOSH (JKKP) in Selangor.
  • The operator must follow the conditions of the special land development permit from the Klang District and Land Office, and the council may cancel the licence if conditions are broken and residents complain.

Bomba's fire certificate asks for the CCC or CF

Larger factories and stores are designated premises under the Fire Services Act 1988 and need a fire certificate (Perakuan Bomba), renewed every year. Bomba's page on the fire certificate lists, among other uses:

New premises must apply as soon as they obtain a CF, a temporary CF or a CCC. The Form I application asks for a copy of the CCC or CF, the building plans certified by Bomba, proof of ownership, the land title, the assessment bill and the business licence. After an inspection the certificate is issued within five days of paying the fee and lasts 12 months. Renewal on Form III is due at least 30 days before expiry, with a RM100 penalty if late.

Bomba is enforcing this now. Full enforcement began in the first quarter of 2026, with a fine of up to RM50,000, five years' jail or both for designated premises without a certificate, the department's deputy director general (operations) said in August 2025, and premises must also set up a fire safety organisation with a fire safety manager and three fire safety officers or the certificate will not be issued, Bernama reported in Awani. Smaller units below the thresholds need no fire certificate, but MBDK's licence checklists still start with Bomba's Klang zone, and her guide to fire protection in a Klang factory or warehouse explains which systems a unit of each size needs.

  • Factories: a single storey of 2,001 m² (about 21,500 sq ft) or more fitted with automatic sprinklers, two storeys where each floor is a separate space and the total floor area exceeds 1,000 m², three storeys or more, and special structures or hazardous processes.
  • Storage and general: more than 7,000 m³, or two storeys or more with more than 1,000 m² of total floor area.

Insurance on a factory without a CCC or CF

None of the sources for this guide says a fire policy is void just because a building lacks a CCC or CF, but insurers look closely at the building. Lulu Loke's fire insurance answers note that factory fire insurance is priced mainly on the construction, the nature of the work, the materials stored, fire protection and the sums insured; that for premises needing a fire certificate, a valid one affects whether and how insurers accept the risk; and that a surveyor may recommend improvements or set conditions.

Under standard fire policy conditions, a change of trade or occupation that raises the fire risk must be endorsed on the policy, or cover for that property stops, as Lulu Loke's guide to fire insurance for a shop or factory explains. A tenant usually insures its own stock, machinery and fit-out, and the landlord the building. Both should tell the insurer in writing what certificate the building holds and what trade runs inside, and get the insurer's answer in writing before the tenancy is signed, not after a claim.

The risks for tenant and landlord

Section 70(27)(f) of Act 133 makes it an offence to occupy, or permit to be occupied, any building or any part of it without a CCC, with a fine of up to RM250,000, up to ten years' jail or both. The tenant occupies; the landlord permits. Both sit inside the same sentence of the law. Beyond that offence, each side carries its own risks:

Land offices act as well. In May 2025 Selangor said it had issued 90 Notice 7A letters under the National Land Code for misuse of agricultural land, with about 500 more due by July, and that the operators of 68 factories on state land in the Klang and Petaling districts, 17 of them in Klang, had to vacate. A tenant in such a unit has no say in how the owner answers those notices.

  • Tenant: a licence that is refused, delayed or limited to a yearly KTK term at a higher fee; no fire certificate for a designated building; a harder conversation with the insurer; and the fit-out, machine moves and staff costs at risk if the council or land office acts.
  • Landlord: the offence of permitting occupation, a unit that is hard to let to tenants who need a licence, and the cost of legalising, from consultants and plans to the land conversion premium.
  • Both: demolition where the land itself is the problem. Selangor demolished 72 factories operating illegally on government land between January and early August 2026, 19 of them in one operation by MBDK and the Klang District and Land Office, The Star reported, and the state's local government chairman said the demolitions hit building owners, businesses and workers.

Checks before you sign a factory tenancy in Klang

Most of these checks cost little and take days, not months. Do them before you pay the deposit:

For the estates around Sungai Kapar Indah, FactoryHub's Kapar and Sungai Kapar Indah industrial area page gives the area's data before you visit. Ms Teh can help you find factories for rent in Klang, Kapar, Meru and Puncak Alam whose CCC or CF you can see before you sign.

  • Ask the owner for a copy of the CCC (Form F) or the CF. In MBDK's area the owner can apply to the Building Department at Pusat Perniagaan Raya Barat, Jalan Raya Barat, Klang, with the latest assessment and quit rent bills, the sale and purchase agreement, a copy of the owner's identity card and a recent photo of the premises.
  • Match the building to the approved plan: count the bays, floors, mezzanines and annexes, and ask which parts were approved later and which never were.
  • Ask in writing whether the unit holds an industrial licence from MBDK or a KTK licence now, and whether any notice from the council, Bomba or the land office has been served. A KTK licence tells you the building is still being legalised.
  • Check the land: a recent official title search (Carian Rasmi) shows the land use category and conditions, which is why MBDK's KTK checklist asks for one or for a land conversion application.
  • If the unit is a designated premises, ask for the current Bomba fire certificate and note its expiry date.
  • Call your insurer with the address, the certificate status and your trade before you sign.
  • With your lawyer, put the answers into the tenancy: the landlord's statement on the CCC or CF, the licence as a condition, what happens to the deposit and the fit-out if the licence is refused or a closure is ordered, and who pays to legalise. FactoryHub's tenancy stamp duty calculator works out the duty on the agreement.

Questions buyers and tenants ask

Is a CF (Sijil Layak Menduduki) the same as a CCC (Perakuan Siap dan Pematuhan)?

Both say a building can be occupied, but they come from two systems. The council issued CFs under the older system; a CCC is issued by the architect or engineer who submitted the plans, under section 70(20) of Act 133. Bomba's fire certificate application accepts a copy of either, and MBSA's and MPKS's licence pages name both.

Can I get an MBDK licence for a factory without CCC in Kapar or Meru?

Not on the normal route, where MBDK's Building Department checks the building for the licence. A factory without approval that is in Selangor's legalisation programme can hold MBDK's KTK industrial licence: one year at a time, at three times the normal fee inside an industrial zone and five times outside, while the owner pursues land conversion, planning and building plan approvals.

Can the landlord be fined if I occupy a factory without a CCC?

Yes, in law. Section 70(27)(f) of Act 133 covers anyone who occupies or permits to be occupied a building or any part of it without a CCC. The fine is up to RM250,000, with up to ten years' jail or both, and it applies to the occupier and to the person who lets them in.

Does every factory in Klang need a Bomba fire certificate?

No, only designated premises. For factories that includes a single storey of 2,001 m² or more with automatic sprinklers, larger two-storey buildings and anything of three storeys or more; for stores, more than 7,000 m³. Smaller units need no certificate, but Bomba's Klang zone still sits on MBDK's licence checklist.

What is a KTK factory (kilang tanpa kebenaran)?

A factory operating without the required approvals, often on land not zoned for industry or on government land. Selangor counted 6,690 on 5,352 lots up to 2019 and 4,170 by May 2025. Those registered in the state's programme have until 31 December 2027 to legalise; those on government land must move out.

How do I get a copy of the CF for a factory in Klang?

Apply to MBDK's Building Department on its CF copy form with the assessment and quit rent bills, the sale and purchase agreement, the owner's identity card and a photo of the premises. A plain copy is RM100 and a certified copy RM200. Copies for personal records go only to the owner, so a tenant usually asks the landlord to apply.

What insurance do I need when renting a factory in Klang?

Usually the landlord insures the building and the tenant insures its own stock, machinery and fit-out, plus public liability for people on site. In low-lying parts of Klang add flood, which is an extension to a fire policy, not part of it. Tell the insurer in writing which certificate the building holds (CCC or CF) and what trade runs inside, and write who insures what into the tenancy.