How much power does your factory need? kVA to amps, checking a Klang unit and upgrading with TNB

Ms Teh Seok Hoon, PEA 4006. Updated

Add up the kW of every machine, compressor, chiller and light, divide by 0.85 (TNB's minimum power factor) to get kVA, then multiply by about 1.44 for amps at 400 V three phase. Check a Klang unit's real supply on the TNB bill's tariff line, the meter type and the main switchboard. Above 100 A an electrical engineer applies to TNB; with a new substation, allow 3 to 12 months.

Key takeaways

  • kVA to amps at 400 V three phase: about 1.44 A per kVA. TNB's handbook puts 100 kVA at about 140 A.
  • A machine list gives kW. Divide by 0.85, TNB's minimum power factor, for a cautious kVA figure.
  • The bill shows the supply level: Non-Domestic Low Voltage means 400 V; Medium Voltage means 11 kV or 33 kV, with maximum demand billed in kW.
  • Up to 100 A, a registered electrical contractor applies on myTNB; above 100 A, a consultant engineer registered with the Board of Engineers applies.
  • TNB's typical lead time is under 3 months without a new substation and 3 to 12 months with one, if council approvals do not slip.
Factory and warehouse hall
Factory and warehouse hall · Illustrative image
kVA to amps, 400 V three phase
about 1.44 A per kVA (100 kVA is about 140 A)
TNB minimum power factor
0.85 below 132 kV
Low voltage ceiling
1,000 kVA (850 kW); above that, medium voltage
New substation needed from
above 350 kVA (about 500 A)
TNB typical lead time, 400 V with substation
3 to 12 months

From the machine list to kVA and amps

Start with the nameplate of everything that will run on site: production machines, motors, air compressors, chillers, ovens, cold rooms, forklift chargers, lighting and office air conditioning. Write each rating in kW; a motor plate in horsepower converts at about 0.746 kW per HP. The total is your connected load.

TNB sizes a supply in kVA, not kW. The two differ by the power factor, and TNB requires users below 132 kV to keep it at 0.85 or higher (TNB supply handbook). TNB's own low voltage charge table uses the same ratio when it puts 1,000 kVA at 850 kW (TNB Jadual 1). So divide kW by 0.85 for a cautious kVA figure; your engineer will use the real power factor of your machines.

Then convert kVA to amps. On TNB's 400 V three phase supply, amps equal kVA × 1,000 ÷ (1.732 × 400), about 1.44 A per kVA. TNB's own figures agree: its supply page lists a 415 V supply of up to 72 kVA as 100 A (TNB), and its handbook writes 100 kVA as about 140 A.

An example, for illustration only: a list adding up to 300 kW is about 353 kVA (300 ÷ 0.85), or roughly 509 A at 400 V. Not every machine runs flat out at the same moment, so the engineer may declare a lower maximum demand after looking at your shifts and start-up sequence. TNB asks for that reasoning: the application lists the connected loads, motor ratings and type of motor starter, and a declared maximum demand must come with the connected load and design calculations (TNB connection guidelines). FactoryHub's factory power calculator gives a quick first number.

  • Connected load (kW): add every nameplate, converting HP at 0.746.
  • kVA: kW ÷ 0.85 as a cautious start (TNB's minimum power factor).
  • Amps at 400 V three phase: kVA × 1.44.
  • Leave room for the next machine: a later upgrade means a new application and a new wait.

Which TNB supply band your number falls into

Once you have kVA, TNB's minimum supply schemes show what the unit needs from the network (TNB connection guidelines). The amps in brackets are at 400 V.

The step that matters most in practice is 350 kVA. Below it, TNB may serve you from an existing substation nearby, subject to its system study; above it, a new substation is required, which means land, a building and more months. A compact substation for an industrial lot goes up to 1,000 kVA and needs about 7.0 m by 4.0 m of land; a conventional single chamber substation building is about 7.6 m by 5.7 m.

  • Up to 100 kVA (about 140 A): three phase from the existing low voltage network, subject to TNB's study; up to 100 A on a whole current meter, above that on a CT meter.
  • Above 100 kVA to 350 kVA (about 140 A to 500 A): underground cable from a feeder pillar or a new or existing substation, subject to TNB's study.
  • Above 350 kVA to 1,000 kVA (about 500 A to 1,400 A): direct underground cable from a new substation.
  • 1,000 kVA up to 5,000 kVA: 11 kV through a TNB switching station; TNB's charge table says loads above 1,000 kVA take supply at medium voltage.
  • 5,000 kVA to 25,000 kVA: 33 kV, and extra land for a main intake may be needed.

What the amps on Klang listings tell you

Ms Teh's live list in November 2026 shows how wide the range is. Of 98 factory and warehouse units that state their power, 6 are at 100 A or less, 89 sit between 101 A and about 1,400 A, which is TNB's low voltage range with a CT meter, and 3 are above it: 2,000 A in Pulau Indah, 2,500 A in Pandamaran and 6,000 A in Meru.

By area, most Puncak Alam units on her list are small: 26 of the 37 that state power are at 200 A or less. Kapar runs from 100 A to 1,200 A, Northport from 150 A to 1,000 A and Westport from 400 A to 1,200 A. A 39,341 sq ft detached unit in Sungai Kapar Indah states 1,200 A, roughly 830 kVA, near the top of the 350 to 1,000 kVA band. FactoryHub's Kapar industrial area page has the estate data for that part of Klang.

A figure far above 1,400 A, like the 6,000 A unit in Meru, is beyond TNB's 1,000 kVA ceiling for low voltage, so a supply that size is taken at medium voltage under TNB's rules. Either way, the number in a listing is what the owner states. Before you plan a production line around it, check it against three things a unit cannot hide.

Is 200 A, 400 A, 600 A or 800 A enough for my factory?

Is 200 A of power enough for a factory?

For light work, often yes. At TNB's 400 V three phase supply, 200 A is about 139 kVA, or roughly 118 kW at a 0.85 power factor. That suits workshops, light assembly and storage, and 26 of the 37 Puncak Alam units on Ms Teh's list that state power are at 200 A or less. Add up your machine list first: compressors, chillers and ovens can pass 118 kW quickly.

What can a factory run on 400 A or 600 A of power?

400 A is about 277 kVA, or roughly 235 kW at a 0.85 power factor; 600 A is about 416 kVA, or roughly 353 kW. The step between them matters: above 350 kVA TNB serves a new supply from a new substation. A 400 A Westport warehouse with 20 loading bays on her list suits storage rather than processing, while 600 A starts to carry small production lines. Size it from your own machine list.

Is 800 A enough for a factory?

800 A is about 555 kVA, or roughly 470 kW at a 0.85 power factor, which sits in TNB's 350 to 1,000 kVA band served at 400 V from a substation. That covers most medium production and cold storage, but a plant whose maximum demand passes about 850 kW moves to medium voltage at 11 kV. On her list, Kapar units run up to 1,200 A and Westport units up to 1,200 A.

Checking what a unit really has: bill, meter, switchboard

The TNB bill. Since 1 July 2025 TNB groups business accounts by supply voltage (myTNB). Non-Domestic Low Voltage General or ToU (old Tariff B or D) means a 400 V supply. Non-Domestic Medium Voltage General or ToU (old Tariff C1, E1, C2 or E2) means a supply above 1 kV, which in Selangor is 11 kV or 33 kV, since 22 kV and 6.6 kV are used only in parts of Johor and Perak. Medium voltage users pay for maximum demand in kW, which TNB defines as twice the highest number of kWh used in any 30 minutes of the month (TNB). Ask the landlord or seller for 12 months of bills: that line shows what the last occupier actually drew.

The meter. An ordinary whole current meter is rated 10 to 100 A. A low voltage supply taking more than 100 A per phase needs current transformers (CTs) and a separate meter panel (TNB metering guidelines). TNB fits CTs by ratio and its charge table links each ratio to a maximum demand band: 400/5 for 181 to 240 kW, 800/5 for 361 to 480 kW and 1200/5 for 601 to 720 kW (TNB Jadual 1). TNB decides the ratio on site, so read it as a pointer, not a guarantee.

The switchboard. The main incoming breaker's rating shows what the installation was built for, not what TNB agreed to supply. Under the Electricity Regulations 1994, an electrical contractor may not wire, rewire or extend an installation without TNB's written approval first (Suruhanjaya Tenaga), so a bigger breaker fitted later does not prove a bigger supply.

The substation and records. Look for a substation on or beside the lot and ask whose it is: TNB has the right to use a substation it takes over to supply other users. Under regulation 67, an installation fed through switchgear rated 100 A or more must be inspected by a competent person at least once a month, and twice a month above 600 V up to 11 kV, so a well run unit has inspection reports and a single line diagram to show you.

  • 12 months of TNB bills: tariff category and, for medium voltage, maximum demand in kW.
  • Meter type: whole current (100 A or less) or CT metered, and the CT ratio on the panel.
  • Main switchboard: incoming breaker rating and the single line diagram.
  • Substation: TNB's or the owner's, and its rating in kVA.
  • Competent person's inspection reports for a supply of 100 A or more.

Applying to TNB for more power at a Klang address

Who applies depends on the load. Up to 100 A, an electrical contractor registered with the Energy Commission applies for you on the myTNB portal; if you are only moving in with no change in load, that step is skipped. Above 100 A, the application must come from an electrical consultant engineer registered with the Board of Engineers Malaysia (TNB supply handbook). TNB registers contractors at the branch where they work, and uses Klang as its example: a contractor working in Klang registers at TNB's Klang branch (TNB).

Above 100 A, TNB's handbook sets out two parts. Part A applies when the work needs council approval, such as a new substation building: the development plan is submitted to the local authority or its One Stop Centre, which asks TNB for comments, and TNB takes up to 14 days at each stage. For addresses in Klang district that council is MBDK; see what MBDK checks, and check which council covers Bukit Raja first, because part of it is in Shah Alam. Part B is TNB's own process: application, document check and system study, a joint meeting to fix the substation, cable route and meter position, a notice of connection charges, payment, site work, handover of the substation, the meter application and finally energising.

If a new substation is needed, the owner provides it. The land is transferred or leased to TNB at a nominal RM10, the substation building is built to TNB's specification and handed over with its Certificate of Completion and Compliance (CCC), and if the land title is not ready TNB asks for a 12 month bank guarantee. TNB also asks for a deposit of about two months' bills, with a bank guarantee encouraged above RM2,000. The application has to include the approved building plans, so settle any unapproved extension on the lot before the engineer files.

What it costs and how long it takes

TNB charges a connection charge up front for a new supply or an upgrade of existing infrastructure (TNB). At low voltage it follows the declared maximum demand. Where no new substation is needed, or its land and building go to TNB for RM10, and the source is within 6 km, TNB's schedule reads as below (TNB Jadual 1).

At medium voltage the charge is RM45 per kW of maximum demand. Medium voltage users also face a connected load charge: RM8.50 for every kW the actual maximum demand falls short of the reference figure, for 6 years after an upgrade from low to medium voltage, or 5 years when an existing medium voltage user adds load. Declaring far more than you will use costs money, so size it from the machine list, not a guess.

TNB's typical lead times, provided council approvals do not slip, are under 3 months at 400 V without a substation, 3 to 12 months at 400 V with a substation, 6 to 12 months at 11 kV and 18 months to 2 years at 33 kV (TNB supply handbook). TNB's service standards add two checkpoints for supply up to 22 kV: the connection charges within 30 days of a complete application, and a scheme needing a new substation carried out within 60 days (TNB GSL and MSL). That 60 days counts only after the charges are paid, the wayleave is obtained and TNB has taken over the substation building (Suruhanjaya Tenaga).

Generation nearby is a separate question. The 1,200 MW Pulau Indah Power Plant beside the Port Klang Free Zone began commercial operation on 1 March 2025 under a 21 year agreement with TNB (The Star), but what a unit receives still depends on the cable, substation and maximum demand agreed for that lot. FactoryHub's Pulau Indah Industrial Park page has the park data there. If a unit is short of power, settle in the offer who applies, who pays the connection charge and the substation, and what happens if TNB's supply comes late. Ms Teh can shortlist units in Klang, Kapar, Meru and Pulau Indah that already carry the amps your list needs.

  • 11 to 37 kW: RM1,700; 38 to 60 kW: RM2,700.
  • 121 to 180 kW (300/5 CT): RM8,100.
  • 241 to 360 kW (600/5 CT): RM16,200.
  • 481 to 600 kW (1000/5 CT): RM27,000.
  • 721 to 850 kW (1500/5 CT): RM38,250; above 1,000 kVA (850 kW) the supply moves to medium voltage.

The TNB bill: tariffs, how it is worked out and how to cut it

How long the upgrade itself takes, and who pays for a substation, is set out in TNB substations and power upgrades: who pays.

Is Tariff E1 the same as Non-Domestic Medium Voltage General?

Yes. Since 1 July 2025 the old Tariff C1, E1 and F1 accounts moved to Non-Domestic Medium Voltage General, and C2, E2 and F2 to Medium Voltage ToU. Old Tariff B and D became Non-Domestic Low Voltage General or ToU. An older bill or listing that says E1 or E2 is describing a medium voltage supply.

How is a factory's TNB electricity bill worked out?

It depends on the supply voltage. Since 1 July 2025 TNB groups business accounts as Non-Domestic Low Voltage or Medium Voltage, each General or Time of Use. Medium voltage users also pay for maximum demand in kW, measured as twice the highest kWh used in any 30 minutes of the month. On a medium voltage ToU tariff, demand in the off-peak period is not charged; the weekday peak runs from 2 pm to 10 pm.

How can a factory in Klang cut its electricity bill?

Start with what TNB measures. Keep the power factor at 0.85 or higher, as TNB requires below 132 kV. On a medium voltage Time of Use tariff, move heavy loads such as chillers or batch runs out of the weekday 2 pm to 10 pm peak, because off-peak demand is not charged. And declare a realistic maximum demand: after an upgrade TNB charges RM8.50 for every kW the actual demand falls short.

More on tariffs and power by industry

Three related questions are answered in more depth on FactoryHub, fellow CID agent Peter Tan's site.

Questions buyers and tenants ask

How many amps is 1 kVA on a three-phase supply?

At TNB's 400 V three phase supply, 1 kVA is about 1.44 A (1,000 ÷ (1.732 × 400)). At 415 V it is about 1.39 A, which is why TNB lists 72 kVA as 100 A. For a quick rule, multiply kVA by about 1.4.

How many amps is a 300 kVA transformer?

On the 400 V side, a 300 kVA transformer gives about 433 A at full load. TNB's distribution substations typically come in 300, 500, 750 and 1,000 kVA ratings, so a 500 kVA unit is about 720 A and a 1,000 kVA unit about 1,440 A.

What is maximum demand on a TNB bill?

Maximum demand is the highest demand in kW in the month, measured as twice the highest number of kWh used in any 30 consecutive minutes. Medium voltage users pay for it per kW. On a ToU medium voltage tariff, maximum demand in the off-peak period is not charged; on weekdays the peak runs from 2 pm to 10 pm.

Can I add machines to my factory without telling TNB?

Not if it means new wiring. The Electricity Regulations 1994 say an electrical contractor may not wire, rewire or extend an installation without TNB's written approval first. If the extra machines push you past the maximum demand agreed with TNB, the supply itself has to be upgraded through a new application.

How do I check a factory's power capacity before I buy it in Klang?

Do not rely on the amps in the listing. Ask the seller for 12 months of TNB bills and read the tariff line, which shows low or medium voltage. Look at the meter: a whole current meter means 100 A or less, a CT meter panel means more. Then read the main breaker rating and the single line diagram, and ask whose substation feeds the lot and its kVA rating.

How do I apply for three-phase power for a factory in Klang?

Through someone registered, not by yourself. Up to 100 A, an electrical contractor registered with the Energy Commission applies for you on the myTNB portal, and TNB registers contractors working in Klang at its Klang branch. Above 100 A, an electrical consultant engineer registered with the Board of Engineers applies, with your connected loads and declared maximum demand, and a new substation may be needed.