Upgrading factory power in Klang: TNB substation or own transformer, cost, waiting time and who pays
Ms Teh Seok Hoon, PEA 4006. Updated
Up to 100 A, a registered electrical contractor applies on myTNB; above that, a consultant engineer applies and TNB studies the network. Above 350 kVA (about 500 A) the lot needs a new substation on land the owner hands to TNB for RM10, and above 1,000 kVA you take 11 kV through your own transformer. TNB's charge follows its schedule, the wait is 3 to 12 months with a substation, and the tenancy decides who pays.
Key takeaways
- TNB treats an upgrade as a new application: up to 100 A through a registered electrical contractor, above 100 A through a consultant engineer.
- Above 350 kVA (about 500 A at 400 V) a new substation is needed; its land and building go to TNB for RM10 and TNB may use it to supply neighbours.
- 3,000 A is about 2,080 kVA, beyond TNB's 1,000 kVA low voltage limit: it means an 11 kV supply and your own transformer.
- For an upgrade TNB charges the difference between the new and the old load charge, for example RM13,500 from the 38 to 60 kW band to the 241 to 360 kW band.
- A new substation needs the owner's title and land form, and MBDK wants the owner's papers too, so settle who pays and who signs in the letter of offer.
- Low voltage limit
- 1,000 kVA (850 kW); above it, 11 kV
- New substation required
- Above 350 kVA at 400 V
- Substation land to TNB
- RM10, transferred or leased
- Medium voltage connection charge
- RM45 per kW of maximum demand
- TNB typical lead time
- 3 to 12 months at 400 V with a substation; 6 to 12 months at 11 kV
Three kinds of upgrade, and which one you are asking for
TNB treats an upgrade like a new supply application and sorts it by load (TNB supply handbook). Work out your load first: add up the machines and convert the total to kVA and amps, as her guide on kVA, amps and checking a unit's power shows, or start with FactoryHub's factory power calculator. Then you know which of three cases you are in.
So a step from 300 A to 600 A is usually the second case, and a step to 3,000 A is the third. A 3,000 A supply at 400 V is about 2,080 kVA (3,000 × 400 × 1.732 ÷ 1,000), roughly twice TNB's low voltage limit, which changes who owns the transformer, what TNB charges and how long you wait.
- Up to 100 A, three phase at 400 V: a registered electrical contractor applies for you on myTNB, and TNB supplies from the existing low voltage network after a capability study. A tenant can apply, with the tenancy agreement pages as proof of occupation (TNB Appendix 2).
- Above 100 A and up to 1,000 kVA (roughly 1,400 A): an electrical consultant engineer registered with the Board of Engineers Malaysia applies. From 100 to 350 kVA TNB may feed you from a feeder pillar or a new or existing substation; above 350 kVA it requires a direct cable from a new substation (TNB connection guidelines).
- Above 1,000 kVA: TNB's schedule says the supply moves to medium voltage (TNB Jadual 1). From 1,000 kVA up to below 5,000 kVA that means 11 kV, fed directly through a TNB 11 kV switching station.
TNB's steps above 100 A, and where Klang's councils come in
When the work needs a new substation building, the council comes first. TNB's handbook calls this Part A: the plans go to the local authority or its One Stop Centre, which asks TNB for comments, and TNB takes up to 14 days at each stage (TNB supply handbook). For Klang, Port Klang, Kapar, Meru and Pulau Indah that council is Majlis Bandaraya Diraja Klang (MBDK). Bukit Raja Selatan is under Shah Alam's council, as her guide on which council covers Bukit Raja explains. Puncak Alam is under Majlis Perbandaran Kuala Selangor (MPKS), which led enforcement in Taman Industri Alam Jaya in April 2025 (NST). MPKS lists an electrical substation in its own fee category for landscape plans, RM50 a submission, and says building work may not start before it approves the plan (MPKS).
Part B is TNB's own process. Your consultant engineer files the application through myTNB and TNB's local distribution office with the approved plans, a site plan showing the substation site, the layout of the substation and of your main switch room, a single line diagram and a list of loads, motors and their starters. Then come TNB's document check and system study, a joint meeting to fix the substation, cable route and meter position, the notice of connection charges, payment, site work, the handover of the substation building, the meter application by your electrical contractor and energising. For a medium voltage supply, energising happens in the presence of your Electrical Testing Engineer.
TNB gives typical lead times of less than 3 months at 400 V without a substation, 3 to 12 months at 400 V with one, and 6 to 12 months at 11 kV, provided local authority approvals are not delayed. Its minimum service levels, for supplies up to 22 kV, are to tell you the connection charges within 30 days of a complete application and to carry out a scheme needing new substations within 60 days (TNB service levels). Most of the waiting sits in steps TNB does not control: council approval, building the substation to TNB's specification and transferring the land, which TNB warns can delay the project.
What it costs: TNB's charge and the bills TNB does not send
TNB's connection charge is the upfront payment for new or upgraded supply infrastructure (TNB). At low voltage it follows the declared maximum demand in TNB's schedule, and for an upgrade TNB's 2025 connection charges book says you pay the difference between the new load charge and the existing one (TNB Connection Charges Book 2025). The rates below apply where the substation land and building go to TNB for RM10, or no substation is needed, and the nearest supply source that can carry the load is within 6 km (TNB Jadual 1).
Medium voltage adds a second charge. For six years after a low voltage user moves up to medium voltage, or five years when an existing medium voltage user adds load, TNB charges RM8.50 for every kW the recorded maximum demand falls short of a reference figure based on what you declared. You declare a final figure and a year by year figure, so a plant that will fill up over three years should say so in the application. If you cancel before TNB starts work, TNB keeps 10% of the charge paid, up to RM5,000.
Then come the costs TNB does not bill, none of which has a published rate: your consultant engineer's fee; the substation land and the building or plinth built to TNB's specification; cable trenching from TNB's substation to your main switch room, the switch room itself and a meter panel (TNB supply handbook); a new main switchboard and the wiring, which needs TNB's written approval before the contractor starts under regulation 11 of the Electricity Regulations 1994; and a deposit of about two months' bills, with a bank guarantee encouraged above RM2,000. Any extra a council imposes, such as laying the cable by horizontal drilling, TNB charges at full cost. Ask the consultant for an itemised quotation that separates TNB's notice from the private works.
- Three phase, non domestic, 11 to 37 kW: RM1,700. 38 to 60 kW: RM2,700.
- 121 to 180 kW: RM8,100. 241 to 360 kW: RM16,200. 481 to 600 kW: RM27,000.
- 721 to 850 kW: RM38,250. Above 1,000 kVA (850 kW) the supply is taken at medium voltage.
- Medium voltage: RM45 per kW of declared maximum demand.
- An illustration: moving from the 38 to 60 kW band to the 241 to 360 kW band costs RM16,200 minus RM2,700, or RM13,500 in TNB charges.
When the lot needs a substation, and when you need your own transformer
Below 1,000 kVA, the substation is TNB's. The owner provides the land and the building: the land is transferred or leased to TNB at a nominal RM10, the building is handed over with its Certificate of Completion and Compliance (CCC), and TNB installs and commissions the equipment inside (TNB supply handbook). TNB keeps the right to use that substation to supply other consumers. A compact substation for a commercial or industrial lot goes up to 1,000 kVA on a plot of about 7.0 m by 4.0 m; a conventional single chamber building is about 7.6 m by 5.7 m, before setbacks (TNB connection guidelines). MBDK's checklist for alteration plans lists an electrical substation under industrial buildings in its plan charges, so on a Klang lot the building goes through the council like any other structure (MBDK).
Above 1,000 kVA, the transformer is yours. TNB supplies only its declared voltages and says consumers can make their own transformation arrangements. At 11 kV you take supply through a TNB switching station, a building of about 7.6 m by 5.7 m, and step it down in your own consumer substation. TNB lays and maintains the service cable to your substation if it runs within 30 m; beyond that the cable is the consumer's cost. In return, 11 kV supplies are normally given alternative circuits, so that supply can be restored within up to 4 hours (TNB connection guidelines).
A medium voltage installation is also a running duty. Under regulations 13 and 67 of the Electricity Regulations 1994, it must be tested on completion by an Electrical Services Engineer and inspected at least twice a month by an Electrical Services Engineer or a Competent Electrical Engineer, against once a month for a low voltage installation fed through switchgear of 100 A or more.
Is there enough supply in the estate?
Nobody can tell from the outside. TNB's supply schemes are subject to its system capability study, and where the study calls for a higher scheme, the higher scheme applies (TNB connection guidelines). The firm answer comes when your consultant engineer files and TNB studies the network at that address. The grid is growing: The Edge reported in June 2026 that TNB's three year capital spending is expected to rise from RM21 billion in 2022 to 2024 to RM43 billion in 2025 to 2027 (The Edge). National spending, though, tells you nothing about the cable to your lot. What you can check before you sign:
Her own list shows how far supply varies by area. Of the 37 Puncak Alam units on it that state their power, 28 are at 300 A or less, and the five Bukit Raja units that state it are at 200 A or 300 A. Pulau Indah has six units at 1,000 A or more, up to 2,000 A, and Pandamaran one at 2,500 A. The only unit above 3,000 A is a 76,074 sq ft detached factory in Meru stating 6,000 A; see the Meru page for the rest. FactoryHub's Kapar industrial area page has the estate data for north Klang.
- The last 12 months of TNB bills: the tariff line and the maximum demand show what the unit already draws.
- The substation: is there one on the lot or beside it, whose is it, and what is its rating? TNB's distribution substations are typically 300, 500, 750 or 1,000 kVA.
- For a medium voltage unit taken over on a change of tenancy, whether the last occupier's connected load charge period is still running: TNB applies the remaining period to the new consumer (TNB Connection Charges Book 2025).
- An early word with TNB: the handbook asks applicants to apply as early as possible at the nearest Kedai Tenaga and to keep TNB informed of progress.
Who pays in a rented factory: landlord or tenant
TNB does not decide it. Its notice of connection charges goes to the consultant engineer and the applicant pays (TNB supply handbook), and either the tenant or the landlord can be the applicant, as long as they bring the supporting documents, such as the rental contract (TNB landlord and tenant booklet). Who carries the cost in the end is a term of your tenancy.
It helps to see what each side gives up. The landlord hands TNB a piece of land for RM10 for good, and TNB may use that substation to supply neighbours. The tenant pays for works that stay with the building: the switch room, cables and main switchboard are built into the property. Her guide on renovating a rented factory explains who owns improvements and what reinstatement means when you leave. Ways to split it that you can put to the owner:
- The tenant pays TNB's charge and its own switchboard; the owner provides the substation land and signs TNB's land form.
- The owner pays and recovers it through the rent or a longer term, since the supply stays with the property.
- The tenant pays, and the owner waives reinstatement of the power works at the end of the tenancy.
- A rent free fit-out period that covers TNB's lead time, and written terms on rent and deposit if TNB's supply comes late or is refused.
When the landlord will not agree
A tenant cannot go around the owner once a new substation is involved. TNB's checklist for supplies above 100 A asks for the owner's name and address, a copy of the land title and Borang A, the certificate for leasing or transferring the substation land (TNB Appendix 4). In Klang, MBDK's alteration plan checklist asks for the owner's identity card, the latest assessment and quit rent receipts and an official title search, and for shophouses and light industrial premises the owner's letter allowing the tenant to renovate, with the tenancy agreement (MBDK). So a refusal leaves these options:
If a signed tenancy already obliges the owner to cooperate and the owner still refuses, that is a contract question for your lawyer, because TNB's and MBDK's forms still need the owner's documents. Ms Teh can help you shortlist units in Klang, Kapar, Meru, Pulau Indah and Puncak Alam that already carry the supply your machines need.
- Ask what the objection is: the land that goes to TNB, the building work, or what is left at the end of the tenancy. Each can be met with an offer on cost, reinstatement or term.
- Size the step down. Up to 350 kVA, TNB may serve you from a feeder pillar or an existing substation, subject to its study, which can avoid a new substation on the owner's land.
- Make it a condition before you sign: the tenancy takes effect only if the owner signs TNB's land forms and the council papers and TNB confirms the supply.
- Choose a unit that already has the supply. It saves both the dispute and months of waiting.
- Do not count on a generator as the fix. TNB's handbook allows standby generators kept separate from its system with an approved changeover, under the relevant laws, as standby supply.
Questions buyers and tenants ask
How much does TNB charge for a three phase supply to a factory?
For a non domestic three phase supply at 400 V, TNB's schedule charges RM1,700 for 11 to 37 kW and RM2,700 for 38 to 60 kW, where no substation is needed or its land goes to TNB for RM10. Above 60 kW the supply is metered through current transformers, with bands from RM4,050 (61 to 90 kW) to RM38,250 (721 to 850 kW). An upgrade pays the difference between the new band and the old one.
How long does TNB take to upgrade a factory's power?
TNB's typical lead times are less than 3 months at 400 V without a substation, 3 to 12 months with one, and 6 to 12 months at 11 kV, provided council approvals are not delayed. For supplies up to 22 kV, TNB's service levels are to tell you the connection charges within 30 days of a complete application and to carry out a scheme needing new substations within 60 days (TNB). Council approval and building the substation usually take longer than TNB's own steps.
How much does a transformer cost for a factory?
Up to 1,000 kVA you do not buy one: TNB installs and owns the equipment in the substation, and you pay the connection charge and provide the land and building. Above 1,000 kVA you take 11 kV and buy your own transformer and switchgear. TNB publishes no price for that equipment, and it varies with rating, type and delivery time, so ask your consultant engineer for supplier quotations before you commit to a unit.
Can my factory's supply go up to 3,000 A?
Yes, but not at low voltage. 3,000 A at 400 V is about 2,080 kVA, above TNB's 1,000 kVA limit for a low voltage supply, so it is taken at 11 kV through a TNB switching station, with your own transformer stepping it down. At RM45 per kW, a declared maximum demand of 1,770 kW would carry a load charge of about RM79,650, and TNB's typical lead time at 11 kV is 6 to 12 months. A unit that already has it, such as the 6,000 A factory in Meru on her list, avoids the wait.
Is a PE jenis padat (pencawang padat) the same as a compact substation?
Yes. TNB's Malay design booklet calls the compact 11/0.4 kV substation Pencawang Elektrik Jenis Padat, or CSU, and makes it TNB's first choice for domestic, commercial and industrial developments (TNB design booklet). For a commercial or industrial lot it goes up to 1,000 kVA on a plot of about 7.0 m by 4.0 m, subject to a matching metering kiosk for a single consumer. PE, pencawang elektrik, is the general term for a distribution substation.
My landlord will not upgrade the power. Can I apply to TNB myself?
Yes, for a supply that needs no new substation: TNB accepts a tenant as the applicant with the tenancy agreement as proof of occupation, through a registered electrical contractor up to 100 A or a consultant engineer above that. Your tenancy's alteration clause still applies to the wiring work. Once a new substation is needed, the owner's title, the land form for TNB and, in Klang, the owner's papers for MBDK are required, so the landlord has to sign.
Can a factory in Klang install a backup generator?
Yes, with two approvals to check. Under the Electricity Supply Act, an installation on TNB supply with a standby generator must be registered with the Energy Commission, and one using its own generation above 5 kW needs a licence unless an exemption applies. The DOE also wants written notification before installing a generator that burns more than 15 kg of liquid fuel an hour. Any generator house or new structure goes to the council.
Which Klang industrial area has the most reliable power supply?
There is no published ranking by estate, so judge the lot, not the area. What decides supply is the substation and feeder serving the unit and the voltage: TNB says medium voltage supplies normally have alternative circuits restored within up to four hours, while 400 V faults may take longer than three hours. The 1,200 MW Pulau Indah Power Plant, running since March 2025, does not by itself raise any lot's agreed demand.
Units in these places
- Semi-D Factory/Warehouse for Rent in Ambang Botanic, 38,910 sq ft, 1000A · RM 71,984 / month
- Factory/Warehouse for Rent in Bandar Baru Klang, 65,000 sq ft, 1000A · RM 110,500 / month
- Detached Factory/Warehouse for Rent in Kapar Bestari, 22,462 sq ft, 200A · RM 50,000 / month
- Industrial Land for Sale in Kapar, 2.34 acres · RM 8,658,005
- Semi-D Factory/Warehouse for Rent in Meru, 25,700 sq ft, Medium Industrial · RM 48,000 / month
- All listings
Updated
Sources
- TNB: Electricity Supply Application Handbook, Supply Application (applications up to and above 100 A, Part A and B, substation land at RM10, lead times, deposits, standby generators)
- TNB: Electricity Supply Application Handbook, Connection Guidelines (minimum supply schemes, substation sizes, 11 kV consumer service cable, security level)
- TNB: Connection Charge (load charge, RM45/kW for medium voltage, connected load charge)
- TNB: Jadual 1, Caj Sambungan bagi Pengguna Voltan Rendah
- TNB: Connection Charges Book 2025 (supply upgrade pays the difference, CLC periods, change of tenancy, cancellation fee, substation land)
- TNB: ESAH Appendix 2, documents for supply applications up to 100 A (tenancy agreement as proof of occupation)
- TNB: ESAH Appendix 4, checklist for supply applications above 100 A (title, Borang A for substation land)
- TNB: Guaranteed and Minimum Service Levels
- TNB: Clarification on tenant and landlord matters regarding electricity supply (2016)
- TNB: Panduan Piawai Reka Bentuk Pencawang Elektrik, Edisi 2.0 (2024)
- Suruhanjaya Tenaga: Electricity Regulations 1994 (regulations 11, 13 and 67)
- MBDK: Borang Senarai Semak Pelan Ubahsuai (PS2024), in force 1 April 2024
- Majlis Perbandaran Kuala Selangor: Panduan, plan approval and landscape plan fees
- NST: MPKS leads another crackdown against businesses run by foreigners, Taman Industri Alam Jaya (Apr 2025)
- The Edge: The beneficiaries of Malaysia's power supercycle (Jun 2026)
Tell Ms Teh what you need
Send the size, power, ceiling height, budget and move-in date you need on WhatsApp, or call her directly.