Overhead crane or goods lift in a Klang factory: crane beams, DOSH approval and the PMA certificate
Ms Teh Seok Hoon, PEA 4006. Updated
An overhead crane needs a building designed for it and three DOSH steps. The columns, brackets and crane beams must be engineered for the crane's wheel loads, and the hook must clear the roof. DOSH then verifies the crane's design, approves its installation and, after a load test, issues a certificate of fitness (the PMA) valid for 15 months. Goods lifts follow the same route. Adding crane beams to an existing factory also needs council approval.
Key takeaways
- Since 1 June 2024, cranes, hoists and lifts come under the Occupational Safety and Health Act 1994 and its 2024 certificate of fitness regulations; the Factories and Machinery Act 1967 is repealed.
- Every powered overhead crane needs DOSH design verification, written approval to install and a certificate of fitness valid 15 months from the inspection; running one without it can cost a fine of up to RM100,000.
- The inspection fee rises with the safe working load: RM750 for a 5 tonne crane, RM950 for 10 tonnes and RM1,200 for 20 tonnes or more.
- Crane beams, brackets and columns belong to the building: Selangor's by-law 69 sets how they are designed, and adding them later needs MBDK, MBSA or MPKS approval.
- Before you rent or buy, ask for the current certificate, the safe working load, the maintenance records and who owns the crane.
- Law since 1 June 2024
- Act 514 and P.U. (A) 99/2024
- Certificate of fitness (PMA)
- Valid 15 months from the inspection
- Inspection fee, 5 / 10 / 20 tonnes
- RM750 / RM950 / RM1,200
- DOSH design verification
- RM300; 15 working days for a complete file
- Who installs cranes over 4,000 kg
- A DOSH competent person or the original maker
The rules since 1 June 2024
Since 1 June 2024, when the Factories and Machinery (Repeal) Act 2022 and the new regulations took effect, cranes have been governed by sections 27B to 27F of the Occupational Safety and Health Act 1994 (Act 514) and the Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024, P.U. (A) 99/2024. Regulation 3 names three kinds of plant that need a certificate of fitness: steam boilers, pressure vessels and lifting machinery, which means any equipment for lifting, raising, transporting or lowering loads. An overhead travelling crane, defined as a crane with a girder that raises and lowers loads and moves on a fixed runway, is one of them, and so is a goods lift.
The Act sets the penalties. As DOSH's guideline to Act 514 sets out, section 27C forbids installing such plant without the Director General's written approval, and section 27D forbids operating it without a certificate of fitness issued by a DOSH officer or a licensed person. Each offence carries a fine of up to RM100,000 or a year in jail, or both. If a DOSH officer serves a notice stopping an uncertified crane and it runs anyway, the fine goes up to RM500,000 or two years. Section 27D also says a certificate ends when the crane is dismantled, repaired or damaged.
Licensed persons are private inspection bodies. The Licensed Person Order 2024 puts overhead cranes in inspection class E, so the inspection can be done by a DOSH officer or by a licensed person holding that class. Papers issued under the old Act were not cancelled: section 4(1) of Act 835, quoted in DOSH's competent person guideline, says registrations and certificates of fitness issued under the repealed Act are now managed under Act 514.
What the building needs: crane beams, columns, foundations and height
An overhead crane runs on runway beams, which the by-laws call crane gantry girders, carried on brackets or columns along the length of the hall. These belong to the building's structure, not to the crane. Selangor's Uniform Building By-Laws say in by-law 69 that crane gantry girders must be designed, under MS EN 1991-1-1, for the forces from vibration, shock from slipping slings, acceleration and braking, and the impact of wheel loads. By-law 68 requires allowance for the dynamic effects of machinery, runways and cranes, and says the increase in imposed loads for installed machinery must not be less than 20%.
The DOSH regulations look at the same point from the crane's side. Regulation 4(1)(h) requires the foundation for any plant needing a certificate of fitness to be adequately designed and built to carry the load it imposes. In practice the crane maker's wheel loads have to be checked by a Professional Engineer against the columns, brackets, runway beams and footings, and by-law 16 requires detailed structural plans and calculations to be submitted to the council before construction starts.
Height is the other limit. The crane's girder, trolley, hoist and hook all sit below the roof, so the hook cannot rise as high as the eave height in a listing. Ask the crane maker for a drawing that shows the hook height at the unit's eave height before you commit. Stated heights on Ms Teh's current list run from 15 ft on semi-Ds in KIIP Kapar to 49 ft eaves at Westport, and a 40 ft semi-D in Meru shows what a taller mid-size unit looks like. The crane's motors add to the electrical load, so check the supply with FactoryHub's factory power calculator.
The same by-law 68 covers large machines that are not cranes: concentrated loads from installed machinery, including impact and vibration, must be designed for, and so must the load of equipment while it is being installed or moved for servicing. A press or a CNC line needs no DOSH certificate unless it is a boiler, a pressure vessel or lifting machinery, but a new foundation or pit for it is structural work for the council. Crane loads travel down the columns to the footings; the floor slab carries the forklifts, racks and machines, which her floor loading guide and FactoryHub's floor loading calculator deal with.
5, 10 and 20 tonne cranes: what changes with capacity
The DOSH paperwork is the same for every powered overhead crane. What changes with size is the fee and who may install it, both tied to the safe working load, which the regulations define as the maximum load stated in the approved design verification. Design verification costs RM300 per design for an overhead crane. The inspection for the first certificate, and each periodical inspection after it, is charged by safe working load in the Sixth Schedule; the bands are in the list below.
Above 4,000 kg the crane must also be installed, and later dismantled, by a DOSH-registered competent person or the original manufacturer. The Seventh Schedule lists overhead travelling cranes, including the monorail type on a standard I or H beam, with a safe working load over 4,000 kg. A 5, 10 or 20 tonne crane is therefore never a job for a general builder.
Can a 20 tonne crane go into a factory built for 5 tonnes? Only if an engineer's check shows the columns, brackets, runway beams and footings can carry the heavier wheel loads, or they are strengthened to a new design. Strengthening is a structural alteration, so it needs the council's approval first. Raising the safe working load of an existing crane is an alteration under the regulations as well: regulation 11 requires the Director General's written approval, with a RM300 processing fee, and a new inspection before the crane runs again.
Small cranes are not exempt either. The Third Schedule only leaves out cranes with a lifting height of no more than nine metres and a working load of no more than 80 kg, air or pneumatic lifting machines up to 500 kg, forklifts and other material handling equipment, dock levellers and a few similar items, and regulation 21 leaves out manual lifting machinery.
- Below 3,000 kg: RM350
- 3,000 kg to below 5,000 kg: RM600
- 5,000 kg to below 10,000 kg, which covers a 5 tonne crane: RM750
- 10,000 kg to below 20,000 kg, which covers a 10 tonne crane: RM950
- 20,000 kg and above, which covers a 20 tonne crane: RM1,200
DOSH approval step by step
DOSH's 2025 guide to design verification for lifting machinery sets the order. Every power-driven crane, whether electric, diesel or pneumatic, needs a valid certificate of fitness, and its design must be verified by the Industrial Safety Division at DOSH headquarters before it is built, installed or used. Registration of the crane can only be applied for once the design verification is granted. The steps, from the guide and the regulations:
- Design verification: filed online in MySKUD through a MyKKP account, by a DOSH-registered competent person firm for a crane made in Malaysia, or by the maker or its appointed agent for an imported one. The file holds the design drawings, calculations to a recognised standard, the catalogue, the safety features and the wire rope or chain certificates.
- Processing: DOSH's client charter is 15 working days for a complete application, and a verification for a crane model is valid for three years.
- Written approval to install: applied for by the owner, the occupier or the holder of the design verification.
- Installation: by a competent person or the original manufacturer for cranes over 4,000 kg, on foundations designed for the load.
- Inspection: a DOSH officer or licensed person load tests the crane at the load in the design verification and tests every safety device, then issues the certificate, valid for 15 months from the inspection date.
- Afterwards: the registration number is marked on the crane (regulation 18), maintenance records are kept (regulation 19), and the periodical inspection falls no earlier than the first day of the twelfth month after the last one.
Goods lifts and hoists
A goods lift is lifting machinery too, so the same DOSH route applies. The regulations define a lift as one carrying persons only, or persons and goods. DOSH's 2025 guide files a lift for goods only, built to EN 81-31, under goods hoists, alongside material hoists and dumbwaiters. The difference shows in the fees: design verification is RM5,000 for a lift and RM300 for a hoist, and the inspection is RM650 for a lift travelling less than 12 metres, against RM350 to RM1,000 for a material hoist depending on its safe working load.
A lift also brings standing duties. Regulation 8(3) requires a maintenance agreement of at least one year with a competent person, and regulation 14 a comprehensive examination at least every three months, or more often if the maker's manual says so. Lifts and hoists must be installed by a competent person under the Seventh Schedule. Dock levellers, tail lifts fixed to a lorry, vertical conveyors and automated storage and retrieval systems are outside the regulations under the Third Schedule.
On the building side, a lift pit, a shaft and new openings in a mezzanine or upper floor are structural work that needs plans. Selangor's by-law 124 only requires a lift in non-residential buildings of more than four storeys, so a goods lift in a one or two storey factory is the occupier's choice; once it is installed, DOSH's rules apply in full.
Council approval in Klang, Shah Alam and Kuala Selangor
Which council approves the crane beams depends on the address. Kapar, Meru, Bandar Bukit Raja, Port Klang and Pulau Indah are under Majlis Bandaraya Diraja Klang (MBDK). Bukit Raja Selatan, the Seksyen 7 side near i-City, is under Majlis Bandaraya Shah Alam (MBSA), as her Bukit Raja page explains, and Puncak Alam is under Majlis Perbandaran Kuala Selangor (MPKS).
MBDK's alteration plan checklist, form MPK/BGN/BORANG-PS-1 in force since 1 April 2024, shows the paper trail to expect. It asks for Form A signed and stamped by the consultant, the CIDB registration of the contractor, a current title search, a copy of the building's CF and, where relevant, a copy of the DOSH approval letter or certificate for mechanical equipment, together with Bomba's approval letter and plan.
MPKS's form JKB05 for additions to existing houses, shops and factories (October 2025) asks for the owner's consent letter when the premises are rented, a copy of the CCC, and reinforcement plans and calculations signed by an engineer registered with the Board of Engineers Malaysia. A tenant who adds crane beams without these approvals has an unapproved alteration, which her guide to illegal extensions covers, and the tenancy should say what happens to the beams and the crane when the lease ends, as her renovation and reinstatement guide explains.
Checks before you rent or buy a factory with a crane
A crane in a listing is only worth something if its papers are in order. A Klang case shows what is at stake: in July 2022 a worker died on the crane route at a metal plant on Jalan Waja in the Bukit Raja Industrial Estate, and Selangor DOSH issued an immediate prohibition notice stopping lifting work with the overhead travelling crane, plus an improvement notice requiring safe work procedures for machinery maintenance, as Malay Mail and Sinar Harian reported. When the crane stops, the line it serves stops with it.
Bringing your own crane needs planning too. DOSH's guide says an overhead travelling crane moved to a new location and built as a permanent structure needs alteration approval even when its safe working load does not change, and regulation 4(3) requires fresh written approval to install at the new address before the inspection. Used overhead travelling cranes that have worked outside Malaysia cannot be verified at all, so a second-hand crane from overseas is not an option.
Ms Teh can shortlist units in Kapar, Meru, Bukit Raja, Pulau Indah and Puncak Alam for a crane operation and ask owners for the crane papers before a viewing.
- Certificate of fitness (PMA): the inspection date, which gives its 15 month validity, and the safe working load it states. The registration number should be marked on the crane.
- Ownership: whether the crane belongs to the landlord, the seller or the outgoing tenant, and that the sale or tenancy agreement lists it. Regulation 5(5) requires the crane's owner to tell DOSH or the licensed person within 30 days after selling, leasing or transferring it, and within 30 days of finding it has fallen into disuse.
- Records: the design verification, inspection reports and maintenance and repair records, which regulations 19 and 20 require at the workplace.
- Building: approved structural plans that show the crane beams, and a CCC or CF that covers them.
- Fit: hook height and span against your loads, and the power supply for the crane motors.
- Lease terms: who books and pays for the periodical inspection, who repairs the crane and the runway beams, and what is reinstated at the end.
- Operators: regulation 15 requires a registered competent crane operator for tower and mobile cranes; for an overhead crane, section 15(2)(c) of the Act still requires the employer to provide the information, instruction, training and supervision needed for safe work.
Questions buyers and tenants ask
Is a PMA the same as a certificate of fitness for a crane?
Yes. PMA is the name owners still use for the crane's certificate of fitness, and DOSH's own 2025 design verification guide asks applicants for the "No. PMA", the number of the lifting machinery certificate of fitness DOSH issued. Under the Act it is the perakuan kelayakan issued under section 27D, valid for 15 months from the inspection date.
Which equipment in a factory must be registered with DOSH?
Plant that needs a certificate of fitness: steam boilers, pressure vessels such as air receivers unless the Second Schedule exempts them, and lifting machinery, which covers overhead, jib and gantry cranes, hoists, goods lifts and passenger lifts. Forklifts and other material handling equipment, dock levellers and lorry tail lifts are outside the certificate regime, but the employer's general duty under section 15 of the Act to keep plant safe still applies.
Can I bring a used overhead crane from overseas into my Klang factory?
No. DOSH's 2025 guide says used lifting machinery that has worked outside Malaysia cannot be verified if it is an overhead travelling crane, a tower crane, a goods or passenger hoist, suspended access equipment or a launching gantry. A used mobile crane from abroad can only be considered if it was built no more than five years before the current year, after a discussion with DOSH headquarters.
Do overhead crane operators in Malaysia need a DOSH licence?
The 2024 regulations require a registered competent crane operator for tower cranes and mobile cranes (regulation 15); overhead cranes are not on that list. The employer still has to provide the information, instruction, training and supervision needed for safe work under section 15(2)(c) of the Act, so trained operators and a written lifting procedure are what an inspector or insurer will ask about.
Does a factory in Bukit Raja Selatan, the Shah Alam Seksyen 7 side, go to MBDK for crane beam approval?
No. Bukit Raja Selatan is under MBSA, while Bandar Bukit Raja and the older Bukit Raja industrial area in Klang are under MBDK. Confirm the council from the title and the assessment bill, then submit the structural plans there. The DOSH approvals for the crane itself go to DOSH whichever council the factory is under.
Who pays for the crane's periodical inspection in a rented factory?
The regulations put the periodical inspection on the owner or occupier and charge a fee for every visit, so the tenancy should say which of you books it, pays the fee and pays for repairs the inspector asks for. The fee follows the safe working load, from RM350 below 3 tonnes to RM1,200 at 20 tonnes and above. If the crane is not available on the day, the inspector may refuse to inspect, the visit is still charged and a new notice has to be filed.
Can a 20 tonne overhead crane be installed in an existing factory?
Only if the structure can carry it. An engineer must check the crane maker's wheel loads against the columns, brackets, runway beams and footings; strengthening them is a structural alteration that needs council approval first, from MBDK in most of Klang. A crane of 20,000 kg and above pays RM1,200 for each DOSH inspection, and anything over 4,000 kg must be installed by a DOSH-registered competent person or the maker.
How much weight can a factory's crane beam carry?
Whatever it was designed for, and only the paperwork tells you. The safe working load is the maximum stated in the crane's approved design verification and on its certificate of fitness (PMA). The runway beams, called crane gantry girders in Selangor's by-law 69, are designed for that crane's wheel loads plus impact and braking. Ask for the approved structural plans and the PMA; a beam's size alone proves nothing.
Units in these places
- Detached Factory/Warehouse for Rent in Kapar Bestari, 22,462 sq ft, 200A · RM 50,000 / month
- Industrial Land for Sale in Kapar, 2.34 acres · RM 8,658,005
- Semi-D Factory/Warehouse for Rent in Meru, 25,700 sq ft, Medium Industrial · RM 48,000 / month
- Detached Factory/Warehouse for Sale or Rent in Meru, 76,074 sq ft, 6000A · RM 35,797,000 or RM 167,363 / month
- Detached Factory/Warehouse for Rent in Bukit Raja Selatan (near i-City Shah Alam), 133,971 sq ft · RM 241,148 / month
- All listings
Updated
Sources
- DOSH (JKKP): Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024, P.U. (A) 99/2024 (gazetted 2 Apr 2024, in force 1 Jun 2024)
- DOSH (JKKP): Panduan Permohonan Verifikasi Reka Bentuk dan Kelulusan Pengubahan bagi Jentera Mengangkat selain Lif, Eskalator dan Laluan Gerak 2025 (updated 31 Jul 2025)
- DOSH (JKKP): Garis Panduan Akta Keselamatan dan Kesihatan Pekerjaan 1994 [Akta 514], Edisi Kedua 2025
- DOSH (JKKP): Perintah Keselamatan dan Kesihatan Pekerjaan (Orang Berlesen) 2024, P.U. (A) 100/2024
- DOSH (JKKP): Garis Panduan Pendaftaran dan Pembaharuan Orang Kompeten 2024
- KPKT (Jabatan Kerajaan Tempatan): Selangor Uniform Building By-Laws 1986, updated to Sel. P.U. 142/2012 (by-laws 16, 68, 69, 124)
- MBDK: Borang Senarai Semak Pelan Ubahsuai, MPK/BGN/BORANG-PS-1 (in force 1 Apr 2024)
- MPKS: Senarai Semak Dokumen Permohonan Pelan Tambahan, rumah kediaman, kedai, kilang sedia ada (JKB05, Oct 2025)
- Malay Mail (Bernama): Selangor DOSH investigates death of worker hit by an iron billet (Aug 2022)
- Sinar Harian: JKKP Selangor siasat punca pekerja maut dilibas bilet besi (Aug 2022)
- FactoryHub: Factory power calculator
- FactoryHub: Floor loading calculator
Tell Ms Teh what you need