Electronics, cleanroom and pharmaceutical factories in Klang: floors, class and approvals
Ms Teh Seok Hoon, PEA 4006. Updated
Electronics factories do not need an anti-static floor by law; the customer's ESD programme decides, and seated work can rely on wrist straps. Pick the cleanroom class from the product's specification under ISO 14644-1, or GMP grades for medicines. Ready cleanroom and licensed pharmaceutical plants are rarely offered in Klang, so most occupiers rent or buy a well-powered shell and fit it out, with NPRA approving the layout for drugs.
Key takeaways
- Anti-static floors are a customer ESD requirement, not a council or Bomba rule; seated operators use wrist straps
- An ESD floor system must test below 1 × 10⁹ ohms with body voltage under 100 V
- ISO 14644-1 has nine classes; Class 100,000 and Class 10,000 are close to ISO 8 and ISO 7
- Pharmaceutical plants need GMP premises, an NPRA layout evaluation and a pre-licensing inspection before the Manufacturer's Licence
- None of Ms Teh's units has a cleanroom fit-out; buyers and tenants usually fit out a well-powered shell
Do electronics factories need anti-static flooring?
Not always. No Klang council, Bomba or building rule asks for an anti-static floor. The requirement comes from the electrostatic discharge (ESD) control programme your customers audit, which in electronics is usually written to ANSI/ESD S20.20 or IEC 61340-5-1. Those programmes care about grounding people and parts, and a floor is only one way to do it.
Under both standards, a seated operator must wear a wrist strap. A standing or walking operator may be grounded either by a wrist strap or by ESD footwear working together with an ESD floor. When the floor is used, the person, footwear and floor are tested as one system: resistance to ground below 1 × 10⁹ ohms, and a walking test that keeps body voltage under 100 V. So an assembly line where everyone sits at grounded benches can run on an ordinary sealed floor, while a store, kitting area or line where people walk with bare boards usually ends up with an ESD floor.
For the building, that means the slab matters more than the coating. ESD epoxy or vinyl needs a level, dry, crack-free slab and grounding points tied back to the earthing system. Read our guide on factory floor cracks and settlement before you price a coating on an older unit, and agree with the landlord in writing whether the floor stays or must be removed when you leave (renovating a rented factory).
- Seated work: wrist straps at grounded benches, the floor is optional
- Standing or walking work: ESD footwear plus an ESD floor, or wrist straps
- Floor system test: below 1 × 10⁹ ohms to ground, body voltage under 100 V
- Building check: slab level and crack-free, grounding points, written reinstatement terms
How do electronics factories choose the cleanroom class?
Start from the product and the customer's specification, not from the building. ISO 14644-1 sorts cleanroom air into nine classes, ISO Class 1 to ISO Class 9, by the maximum number of airborne particles per cubic metre. A lower number is cleaner, and each class allows ten times the particles of the class below it. At particles of 0.5 micron and larger, the limits are 3,520 per cubic metre for ISO Class 5, 352,000 for ISO Class 7 and 3,520,000 for ISO Class 8.
Older drawings and tenders in Malaysia still use the names of the withdrawn US Federal Standard 209E. Class 100 lines up with ISO Class 5, Class 10,000 with ISO Class 7 and Class 100,000 with ISO Class 8. The match is close but not exact, so a room should be classified to ISO 14644-1 today.
Three points decide the class you write into a tender. First, the cleanliness your product or your customer states, at the particle sizes it names. Second, the occupancy state: a room can be classified as built, at rest or in operation, and a room that passes at rest can fail once people and machines work in it. Third, cost: every step to a cleaner class needs more filtered air, more fan and air-conditioning power and stricter gowning, so pick the least strict class the specification allows and keep the clean zone as small as the process lets you. Many electronics plants only need ESD control on most of the floor and a classified room for one process.
Medicines follow a different scale. Malaysia's drug regulator, NPRA, inspects pharmaceutical plants against the PIC/S Guide to Good Manufacturing Practice, which Malaysia adopted when it joined PIC/S on 1 January 2002 (NPRA). Sterile work there uses GMP grades A to D, so a pharmaceutical tender should be written against those grades, with ISO 14644-1 used for the particle test.
What does Class 100,000 or Class 10,000 mean?
They are names from the withdrawn US Federal Standard 209E, which counted particles per cubic foot. Class 100,000 is close to ISO Class 8 and Class 10,000 is close to ISO Class 7. Ask for the room to be classified and tested to ISO 14644-1, with the occupancy state stated.
How much does it cost to convert a factory into a cleanroom?
There is no published rate per square foot: the cost follows the class, the size of the clean zone and the process utilities. Public contract values show the scale. In June 2026 Sum Technology took a RM20.46 million contract to design and build a Class 100,000 (ISO Class 8) cleanroom facility at K Test Malaysia's plant in Ipoh, covering walkable ceilings, ESD vinyl flooring, liquid nitrogen piping, oil-free compressors and the Bomba submissions (The Star). In November 2026 Critical Holdings reported RM65 million of contracts for a new cleanroom production floor with its mechanical, electrical and process utilities (The Edge). Get itemised quotes for your own class and area, and add the TNB upgrade and the council approvals.
What air-conditioning and filtration does a pharmaceutical factory need?
Whatever its GMP grades call for: NPRA assesses drug plants against the PIC/S GMP guide, and its FAQ says a manufacturer may submit the plant layout for evaluation on form BPFK-503 before building (NPRA). For a sense of the detail, the Ministry of Health's guide to its own pharmacy facilities asks sterile preparation rooms for a dedicated HVAC system, HEPA filters changeable from outside the room, no more than 22°C and 55 ± 5% humidity, and 10 to 15 Pa more pressure in each cleaner room (MOH).
Where can you rent a factory for pharmaceutical manufacturing in Klang?
A ready, licensed pharmaceutical plant almost never comes up for rent. What you rent in Klang is a clean, well-powered shell, and you fit out the GMP areas yourself. NPRA's own guidance says registered products must be made in GMP-compliant premises that are also licensed by the local council, the Department of Environment and/or the Fire and Rescue Department, and it gives new entrepreneurs two routes: build their own factory or appoint a GMP-compliant contract manufacturer (NPRA).
If you build, the order matters. NPRA lets a manufacturer submit the plant layout for evaluation (form NPRA/431/12-3) before construction, then a pre-licensing GMP inspection is a condition for registering products and applying for a Manufacturer's Licence from the Drug Control Authority (NPRA). Cosmetic makers need no Manufacturer's Licence but must still follow GMP once their products are notified. Medical device makers fall under a different law: the Medical Device Act 2012 requires an establishment licence, and a manufacturer needs MS ISO 13485 certification from a conformity assessment body registered with the Medical Device Authority (MDA).
Local practice shows why rented GMP plants are rare. Duopharma's plants in Klang are its own: its 1994 plant in Taman Klang Jaya housed QC, QA, oral solid dosage and haemodialysis lines, and in 2016 it began a RM103.7 million plant with a RM37.1 million warehouse there (The Edge, March 2016). Its specialised biotechnology facility in Klang, K5, had still not been launched in September 2026 while the group built its product pipeline (The Edge, September 2026).
For a tenant, the practical answer is a long lease on a detached or large semi-D unit with spare power, then your own fit-out. Two of Ms Teh's units show the kind of shell to ask about: a detached factory in Meru with 6,000 A, for sale or rent and a 65,000 sq ft factory in Bandar Baru Klang with 1,000 A for rent. Neither has a GMP or cleanroom fit-out. Because the fit-out is costly and must be inspected, ask for a lease long enough to recover it, with renewal options and clear reinstatement terms (how long a factory lease should run).
Where are cleanroom factories for sale in Klang?
Very few are offered with a working cleanroom, and none of Ms Teh's current units records one. A cleanroom is built for one process and one owner. When that owner sells, the room is often stripped out, moved or sold with the business rather than with the building. Buyers in Klang usually buy a sound shell and build the clean zone they need, sized to their own process.
Where to look depends on the class of industry. Electronics plants already approved at Klang addresses include computer workstations in Bandar Sultan Suleiman, display technology in Taman Industri Alam Jaya, Puncak Alam and battery pack assembly in Bukit Raja; our guide on which Klang industrial area suits your industry lists them with the source. Check the industrial class of a lot before you buy (light, medium and heavy industry), and read our notes on Taman Industri Alam Jaya and Meru if those areas are on your list.
If a seller does offer a cleanroom, treat it as equipment and ask for the papers: the latest ISO 14644-1 classification certificate (class, particle sizes, occupancy state, date and testing party), air-conditioning and filter maintenance records, and the drawings. For a pharmaceutical buyer, the room only counts once NPRA accepts it in your own licence. NPRA's July 2026 guidance treats upgrading a production floor to a cleanroom as a revision of the existing premises layout with a RM500 processing fee, and a new manufacturing site as a new layout with a RM1,000 fee, with a GMP inspection if needed (NPRA).
What to check in the building before a cleanroom or ESD fit-out
Electronics is still growing: MIDA reported RM28.5 billion of approved investment in Malaysia's electrical and electronics sector in 2025 (MIDA, May 2026). Most of that money goes into fit-out and machines, so the shell you choose has to carry them. These are the checks Ms Teh runs with buyers and tenants before a clean or ESD project is priced.
Power and supply security come first, because air handling runs around the clock. TNB's connection guidelines say supplies at 11 kV, 22 kV and 33 kV are normally given alternative circuits so supply is restored within up to 4 hours, except for natural disasters or weather (TNB). A plant that cannot lose a batch should plan for a medium voltage supply; see factory power, kVA and amps and our guide to high-spec factories.
- Power: spare amps for air handling, and a medium voltage supply where downtime is costly
- Floor: a level, crack-free slab for ESD coatings and heavy air-handling units
- Height: room above the planned clean ceiling for ducts, filters and fan units
- Roof and walls: no leaks or loose cladding over the future clean zone
- Water and wastewater: supply, storage and effluent rules (water, gas and fibre, factory wastewater)
- Approvals: the lot's industrial class, council licence, Bomba and, where it applies, a MIDA manufacturing licence
Should an electronics plant choose Penang, Selangor or Johor?
Choose by where your supply chain already is. Penang is the deepest E&E cluster: its chief minister said in August 2026 that the state's E&E exports passed RM350 billion in the first half of 2026 and consistently make up more than 60% of Malaysia's E&E exports (The Star), and InvestPenang counts more than 6,500 local suppliers in automation, plastics, electronics and other trades (InvestPenang). A semiconductor back-end or test plant that depends on those suppliers usually starts there.
Johor and Selangor led the states for approved investment in January to September 2026, at RM99.7 billion and RM87.9 billion, against RM41.1 billion for Penang (MIDA), though those totals cover every sector. Selangor's case for E&E is its market, its ports and its spread of estates: Port Klang handled a record 15.14 million TEU in 2025 (Malay Mail), and Selangor's 2022 to 2024 approvals put semiconductor and circuit board plants mostly in Puchong, Shah Alam, Bangi and Petaling Jaya, with assembly work around Klang such as computer workstations in Bandar Sultan Suleiman and battery packs in Bukit Raja (Dewan Negeri Selangor). If your customers and imports run through Klang Valley and Port Klang, a Selangor shell with the power, floor and class set out above is the practical start.
How Ms Teh can help with the search
Send Ms Teh the floor area you need, the power load, whether you need ESD control only or a classified room and at what class, and whether you want to buy or rent. She can shortlist shells in Klang, Meru, Bukit Raja and Puncak Alam that meet the building checks above, and arrange viewings with your cleanroom contractor so the fit-out is priced before you sign. For food plants, see our guide to food factory requirements; for plastics and glove lines, plastics, recycling and glove factories.
Questions buyers and tenants ask
Is an ESD floor the same as an epoxy floor?
No. A plain epoxy coating is not ESD flooring. Only an ESD grade floor that tests below 1 × 10⁹ ohms to ground, with the footwear in use and a walking test under 100 V, counts in an ESD control programme to ANSI/ESD S20.20 or IEC 61340-5-1.
Is a dust-free room the same as a cleanroom?
In everyday talk, yes: dust-free room, clean room and cleanroom (无尘室 or 洁净室 in Chinese) all mean a controlled space. What matters is the class: ask which ISO 14644-1 class the room was tested to, at which particle sizes and in which occupancy state.
Can I build a cleanroom inside a rented factory in Klang?
Yes, with the landlord's written consent and any council and Bomba approvals the works need. Agree in the tenancy who owns the room, whether it must be removed when you leave, and a lease long enough to recover the cost.
Does a pharmaceutical factory need NPRA approval before renovation?
NPRA lets a manufacturer submit the plant layout for evaluation before building (form NPRA/431/12-3), and a licensed plant that upgrades a production floor to a cleanroom files a layout revision with a RM500 fee. A pre-licensing GMP inspection comes before the Manufacturer's Licence.
Do cosmetic or medical device makers follow the same rules as drug makers?
No. Cosmetic makers need no Manufacturer's Licence from NPRA but must follow GMP once their products are notified. Medical device makers need an establishment licence under the Medical Device Act 2012 and MS ISO 13485 certification.
Units in these places
- Detached Factory/Warehouse for Rent in Kapar Bestari, 31,293 sq ft, 200A · RM 68,845 / month
- Semi-D Factory/Warehouse for Rent in Ambang Botanic, 38,910 sq ft, 1000A · RM 71,984 / month
- Semi-D Factory/Warehouse for Rent in Meru, 25,700 sq ft, Medium Industrial · RM 48,000 / month
- Detached Factory/Warehouse for Sale or Rent in Meru, 76,074 sq ft, 6000A · RM 35,797,000 or RM 167,363 / month
- Cluster Factory/Warehouse for Sale in Eco Business Park V, 4,211 sq ft, 150A · RM 3,850,000
- All listings
Updated
Sources
- NPRA: Frequently Asked Questions about GMP inspection (Apr 2023)
- NPRA: Drug Registration Guidance Document, Appendix 27 Inspection (Jul 2026)
- NPRA: FAQs about foreign GMP inspection, PIC/S membership since 2002 (Jan 2024)
- Medical Device Authority: Guidance document, licensing for establishment (second edition)
- MIDA: MIDA positions talent at the centre of Malaysia's semiconductor growth (May 2026)
- TNB: Electricity supply connection guidelines, supply security levels
- The Edge Malaysia: CCM Duopharma to spend RM140.8m on new plant, warehouse (Mar 2016)
- The Edge Malaysia: Duopharma eyes biologics, export growth as insulin market share shrinks (Sep 2026)
- The Star: Sum Tech's unit inks RM20.46mil clean room contract (Jun 2026)
- The Edge Malaysia: Critical Holdings bags RM65 mil cleanroom contracts from multinational (Nov 2026)
- NPRA: Frequently asked questions about GMP inspection (Jan 2022)
- Ministry of Health, Pharmaceutical Services: Guides to the development of pharmacy facilities
- The Star: Penang records RM350bil in E&E exports in 1H26 (Aug 2026)
- InvestPenang: Electrical and electronics
- MIDA: Malaysia records RM350.4 billion in approved investments in the first nine months of 2026 (17 Nov 2026)
- Dewan Negeri Selangor: written answer 290, appendix, manufacturing projects approved 2022 to 2024
- Malay Mail: Port Klang hits record 15.14 million TEUs in 2025 (Mar 2026)
Tell Ms Teh what you need
Send the size, power, ceiling height, budget and move-in date you need on WhatsApp, or call her directly.